Applied Digital says 250 MW of critical IT load is now ready for service at its fully leased Polaris Forge 1 campus in North Dakota, and secures access to up to 1 GW of potential power in Finland

Applied Digital said on October 2, 2026 that three more 25 MW data halls reached Ready for Service at Polaris Forge 1 in Ellendale, North Dakota. That completes Building 2 at 150 MW and brings the campus's fully operational critical IT load to 250 MW, of 400 MW contracted at full buildout. The campus is fully leased; Applied Digital previously disclosed CoreWeave as tenant for all 400 MW. On October 6, the company said it signed an agreement giving it access to up to 1 GW of potential power capacity in Finland, with initial power availability anticipated beginning in 2028. [Source 1] [Source 2] [Source 3]

Applied Digital says 250 MW of critical IT load is now ready for service at its fully leased Polaris Forge 1 campus in North Dakota, and secures access to up to 1 GW of potential power in Finland
All news & analysisDevelopment & PowerEllendale, North Dakota (Polaris Forge 1); Finland, site not disclosedPolaris Forge 1: 250 MW of critical IT load described by the company as fully operational, including 75 MW reaching Ready for Service on October 2, 2026; 400 MW leased at full buildout. Finland: agreement for access to up to 1 GW of potential power capacity, initial availability anticipated from 2028; announced October 6, 2026. As of October 6, 2026.

Disclosed terms

New capacity ready for service
75 MW of critical IT load across three 25 MW data halls [1]
Operational at campus
250 MW of critical IT load [1]
Contracted at full buildout
400 MW of critical IT load, fully leased [1]
Tenant
CoreWeave, 400 MW across three leases, about $11 billion total anticipated lease revenue (August 2025) [3]
Finland power access
Up to 1 GW of potential power capacity, initial availability anticipated from 2028 [2]

The disclosure and our analysis

Evidence dates

Evidence: Applied Digital press releases dated October 2, 2026 (Polaris Forge 1) and October 6, 2026 (Finland); Applied Digital press release dated August 29, 2025 (CoreWeave leases). Applied Digital scheduled its fiscal first quarter 2027 results call for October 7, 2026, after this draft was prepared; any new disclosures there are not reflected.

Polaris Forge 1: what Applied Digital disclosed

Applied Digital (Nasdaq: APLD) said it achieved Ready for Service for the second phase of Building 2 at Polaris Forge 1, delivering an additional 75 MW of critical IT load across three 25 MW data halls. [Source 1]

Capacity, all on a critical IT load basis, as of October 2, 2026: [Source 1]

**Building 1:** 100 MW, completed earlier.

**Building 2:** 150 MW, now complete. Its first 75 MW phase was delivered earlier and the second 75 MW phase on October 2.

**Fully operational at the campus:** 250 MW.

**Contracted at full buildout:** 400 MW. The company calls the campus fully leased.

The campus is in Ellendale, North Dakota, where Applied Digital has operated since 2021. [Source 1]

The tenant and lease terms

The October 2 release does not name a tenant. In August 2025, Applied Digital said it had finalized a third lease with CoreWeave at Polaris Forge 1, bringing CoreWeave's total to 400 MW across three leases, with about $11 billion of total anticipated contracted lease revenue. The first two leases, 100 MW and 150 MW, have terms of about 15 years. At that time, the company expected the third building, 150 MW, to be ready for service in 2027. [Source 3]

Finland: what Applied Digital disclosed

On October 6, 2026, Applied Digital said it entered into an agreement providing access to up to 1 GW of potential power capacity in Finland, its first development opportunity outside the United States. It plans an AI Factory campus capable of scaling to as much as 1 GW. Initial power availability is anticipated beginning in 2028. The company says it has begun marketing the site and is in discussions with hyperscale customers. Future investment depends on customer demand, commercial milestones and regulatory and development requirements. [Source 2]

The release does not identify the municipality, the counterparty, or what kind of agreement it is, such as a grid connection reservation, a land option or a supply contract. The 1 GW is described as potential power capacity, not critical IT load. [Source 2]

Buyer analysis

This is our analysis.

**Ellendale is delivered capacity, but it is not open space.** The 250 MW is the company's figure for critical IT load ready for service. All 400 MW at the campus is contracted. Nothing here is available to new customers.

**Delivery pace is the useful signal.** Applied Digital has now delivered 250 MW of critical IT load at one site across three phases. The remaining 150 MW sits in Building 3, which the company last dated to 2027. Buyers comparing wholesale providers should ask for evidence of completed phases like this, not just announced pipelines.

**Finland is an option, not a campus.** Up to 1 GW of potential power with first availability in 2028 is an early stage site. There is no disclosed location, customer or construction date yet. Treat it as a marker for future Nordic supply rather than near-term capacity.

What remains unknown

The reviewed sources do not disclose current lease rates at Polaris Forge 1, the timing of Building 3 beyond the 2027 expectation stated in August 2025, utility service or total power capacity at the campus, or whether CoreWeave remains the sole tenant after any assignments. For Finland, they do not disclose the site location, counterparty, agreement type, power source, grid operator approvals, cost or the critical IT capacity planned. Applied Digital's fiscal first quarter 2027 results, due October 7, 2026, were not reviewed.

Sources

  1. Applied Digital, press release · Published 2026-10-02
  2. Applied Digital, press release · Published 2026-10-06
  3. Applied Digital, press release · Published 2025-08-29

Related reporting

Development & Power

Denton, Texas data center permit S26-0006 seeks a Specific Use Permit for 23.8 acres off E. University Dr.

A Specific Use Permit application for a data center on 23.8 acres in Denton, Texas, south of E. University Dr. and west of Geesling Rd., was submitted to the City of Denton on November 9, 2026. The city's planning record lists it as case S26-0006, project name Birddog, on land zoned Light Industrial and not platted. Its status was Under Review as of November 13, 2026. The record lists no megawatts, end user or hearing date. [Source 1]

South of E. University Dr. and west of Geesling Rd., Denton, Denton County, Texas · Proposed (Specific Use Permit application S26-0006 submitted November 9, 2026; city status Under Review as of November 13, 2026). No hearing date set in the record. No megawatt figure, tenant or end user disclosed.
Read the analysis
Development & Power

Entergy Arkansas plans a second phase of service for Google's West Memphis data center campus, with about $600 million of grid work and a 440 MW solar contract paid for by Google

Entergy Arkansas announced on October 19, 2026 a second phase of electric service for Google's data center campus in West Memphis, Arkansas. The utility says the phase needs about $600 million of planned investment plus a power purchase agreement, all covered by Google: two battery systems, a 440 MW (ac) solar contract, an expanded Galet substation and two new 230 kV lines to serve the expanded campus. The expansion still has to be submitted to the Arkansas Public Service Commission; Entergy targets service in 2028 if it is approved. Entergy listed the expanded Google agreement among its third quarter highlights on November 2. [Source 1] [Source 2]

West Memphis, Crittenden County, Arkansas · Announced October 19, 2026; to be submitted to the Arkansas Public Service Commission for approval. Pending approval, Entergy expects service in 2028. Not approved as of November 2, 2026.
Read the analysis
Development & Power

San Antonio now requires a City Council vote on every new data center after a 9-2 code change

San Antonio City Council voted 9-2 on October 29, 2026 to pass data center regulations proposed by District 6 Councilmember Ric Galvan. The approach requires a Specific Use Authorization, a zoning approval voted on by council, for each new data center, rather than allowing data centers by right where they meet set standards. The mayor said the change ensures council can review each data center application. The final signed ordinance was not posted in the sources we reviewed. [Source 1] [Source 2] [Source 4]

San Antonio, Bexar County, Texas (city limits) · Approved: City Council passed the data center code change 9-2 on October 29, 2026. Final signed ordinance not reviewed.
Read the analysis