Applied Digital and Soluna sign an agreement to form a joint venture for a planned 50 MW critical IT AI data center at Dorothy 3 in Briscoe County, Texas

Soluna Holdings disclosed on October 21, 2026 that it signed a subscription agreement on October 20 with affiliates of Applied Digital to form a jointly owned project company. The company would develop a planned 50 MW critical IT data center for AI and high performance computing at Soluna's Project Dorothy 3 site near Silverton in Briscoe County, Texas, next to the Briscoe Wind Farm, which Soluna describes as a 150 MW wind farm. Applied would hold 51% and Soluna 49%. Closing is conditional, including a county tax abatement vote, and is expected on or before December 1, 2026. ChronoScale, which Soluna says Applied majority owns, has signed only a nonbinding letter of intent to lease the facility. [Source 1] [Source 2]

Applied Digital and Soluna sign an agreement to form a joint venture for a planned 50 MW critical IT AI data center at Dorothy 3 in Briscoe County, Texas
All news & analysisDevelopment & PowerProject Dorothy 3, near Silverton, Briscoe County, TexasProposed. Subscription agreement signed October 20, 2026; joint venture closing conditional on a Briscoe County tax abatement vote and other conditions, expected on or before December 1, 2026. Tenant is a nonbinding letter of intent only. The filing says some site development work has begun; reviewed sources do not establish building construction, energization, a lease or availability. As of October 23, 2026.

Disclosed terms

Critical IT capacity
50 MW critical IT; about 75 MW gross capacity, per the filing [1]
Ownership
Applied affiliate 51%; Soluna affiliate 49% [1]
Applied cash contribution
$19,515,306, less qualifying pre closing payments [1]
Soluna contribution value
$18,750,000 attributed to the ground sublease [1]
Expected closing
On or before December 1, 2026; no later than December 31, 2026 with extensions [1]
Planned tenant
ChronoScale, nonbinding letter of intent only [2]
Power source
Briscoe Wind (150 MW wind farm, per Soluna) and the grid, subject to definitive documents [2]

The disclosure and our analysis

Evidence dates

Evidence: Soluna Holdings Form 8-K reporting a subscription agreement dated October 20, 2026, filed October 21, 2026; Soluna press release dated October 21, 2026, furnished as Exhibit 99.1 to a separate Form 8-K. Both read October 23, 2026.

What Soluna disclosed

Soluna and certain of its affiliates entered into a subscription agreement with affiliates of Applied Digital to form STX JV Holdings LLC, the project company. At closing, an Applied affiliate would acquire 51% of the project company's membership interests and a Soluna affiliate would acquire 49%. [Source 1]

The filing says the project company will develop a data center referred to as Dorothy 3A, consisting of approximately 75 megawatts of gross capacity, or 50 megawatts of critical IT capacity, in Briscoe County, Texas. The press release describes the project as a planned 50 MW critical IT data center for AI and HPC at Project Dorothy 3, Soluna's development site near Silverton. [Source 1] [Source 2]

Soluna describes Dorothy 3 as co located with Briscoe Wind, which it calls a 150 MW wind farm, near its Dorothy 1 and Dorothy 2 projects. Subject to definitive documentation, Soluna says Phase 1 (50 MW critical IT) is expected to draw power from both Briscoe Wind and the grid. The 150 MW figure is the wind farm's size as Soluna states it; the release does not say how much of that output would serve the data center. [Source 2]

Disclosed economics

1. **Soluna's contribution:** a ground sublease interest with an attributed value of $18,750,000, plus a newly formed intermediate holding company. [Source 1]

2. **Applied's contribution:** $19,515,306 in cash, reduced dollar for dollar by qualifying development and long lead equipment payments Applied makes before closing. [Source 1]

3. **Pre closing costs:** The filing says certain development work related to the project has begun at the site and will continue through closing, and certain equipment may be procured, at Applied's cost. If the deal terminates without closing, Soluna's investor entity must reimburse 80% of those funded costs, up to $45 million, on a schedule with interest. [Source 1]

4. **Ground sublease:** at closing, a Soluna entity would enter a 99 year ground sublease with STX-01 LLC, a project company subsidiary. [Source 1]

5. **Warrant:** Soluna would issue Applied or an affiliate a seven year warrant for up to 7,644,444 Soluna common shares at $0.74 per share. [Source 1]

Conditions and status

Closing is expected on or before December 1, 2026. That date can extend by 30 days if only the tax abatement vote remains outstanding, or by 10 days if only title deliverables remain, but not beyond December 31, 2026. Conditions include the tax abatement vote, a leasehold title policy, ChronoScale's and the parties' internal approvals, and execution of the LLC agreement and other transaction documents. The filing says that, other than a form of assignment agreement, the ancillary agreements, including the data center lease with ChronoScale, the construction contract and the ground leases, had not been finalized as of the report. [Source 1]

ChronoScale Holdings, which Soluna's release describes as majority owned by Applied, has signed a nonbinding letter of intent to lease the planned facility. Soluna says there is no assurance a definitive lease will be signed on those terms or at all. [Source 2]

On our status vocabulary, this project is Proposed as of October 23, 2026. A signed subscription agreement exists, but the joint venture has not closed, the reviewed sources do not show the tax abatement approved, and the facility is not Leased. The filing says development work has begun at the site but does not describe its scope, so we do not treat it as evidence that the data center is Under construction. Nothing reviewed establishes energization or availability.

Buyer analysis

This is our analysis, not a company statement. The planned tenant is an Applied affiliate, so the first 50 MW of critical IT appears intended for related party use rather than open colocation inventory. Buyers looking at West Texas wind sited capacity should treat Dorothy 3 as a development to watch, not a source of near term space.

The structure is worth noting for operators. A power site developer is contributing land and power related assets for a minority stake, while a builder and operator funds the project and holds control. Applied is already paying for site development work before closing, protected by an 80% reimbursement obligation capped at $45 million if the deal fails.

The Briscoe County tax abatement vote is the next public milestone to check. It should appear on county commissioners court agendas.

What remains unknown

The reviewed sources do not disclose the data center lease rate or term, the share of Briscoe Wind output dedicated to the facility, the grid interconnection capacity or utility for the site, the scope of development work under way, a construction schedule for the building, an energization date, total project cost, financing beyond Applied's cash contribution, or the date of the Briscoe County tax abatement vote. The filing does not define how the 75 MW gross figure relates to utility service capacity.

Sources

  1. Soluna Holdings, Form 8-K (subscription agreement of October 20, 2026) · Published 2026-10-21
  2. Soluna Holdings, press release on Applied Digital partnership (SEC Exhibit 99.1) · Published 2026-10-21

Related reporting

Development & Power

PG&E reports 12,870 MW of data center load in its pipeline and lists large load beyond an initial 1.8 GW as work to be delayed or deferred

PG&E's third quarter 2026 earnings presentation, furnished October 22, 2026, shows 12,870 MW of new data center load in its pipeline as of September 2026, up from 12,710 MW in June. Most of it, 8,350 MW, is at the application and preliminary engineering stage. PG&E says it has energized 174 MW of new data center projects since 2024. A capital plan slide lists large load beyond an initial 1.8 GW among work that will be delayed or deferred. [Source 1] [Source 2]

PG&E service territory, Northern and Central California (no project sites disclosed) · Mixed pipeline as reported by PG&E as of September 2026: 8,350 MW at application and preliminary engineering, 3,880 MW in final engineering, 400 MW with an executed interconnection construction agreement, 240 MW in construction; 174 MW energized since 2024. Large load beyond an initial 1.8 GW listed as delayed or deferred work. None of this establishes available colocation capacity. As of October 22, 2026.
Read the analysis
Development & Power

FERC accepts PJM's 50 MW large load definition and registry but rejects its plan to connect new large loads ahead of new capacity

The Federal Energy Regulatory Commission on October 9, 2026 accepted two parts of PJM Interconnection's large load proposal: a definition of Large Load as 50 MW or more of cumulative peak load at a single electrical site, and a Large Load Registry, both effective October 12, 2026. It rejected the rest, including the Interim Resource Adequacy Service that would have let new large loads connect before matching new capacity in exchange for curtailment exposure. [Source 1]

PJM Interconnection region · Approved in part. FERC accepted the Large Load definition and Large Load Registry effective October 12, 2026 and directed a PJM compliance filing within 30 days. IRAS, the new capacity designation requirement, Bring Your Own New Capacity rules and the demand curve exclusion were rejected. As of October 9, 2026.
Read the analysis
Development & Power

Stafford County, Virginia approves the Accokeek Center data center rezoning, with about 122 MW of Dominion service planned at full build-out

Stafford County supervisors voted 4-3 on October 7, 2026 to rezone about 121 acres for the Accokeek Center data center campus and to approve a Dominion substation permit, according to local reports. County documents describe up to 590,000 square feet in two buildings between U.S. 1 and Interstate 95. The applicant says the project is expected to need about 122 MW of electrical service at full build-out. [Source 1] [Source 3] [Source 4]

West side of Richmond Highway (U.S. 1), about 2,500 feet north of Eskimo Hill Road, Falmouth District, Stafford County, Virginia · Approved. Rezoning to M-2 and the substation conditional use permit approved 4-3 on October 7, 2026, per local reports; county minutes were not yet posted when checked on October 14, 2026. Site plan and utility approvals remain. The applicant's fiscal analysis expects the first building to operate in 2029. Not available. As of October 14, 2026.
Read the analysis