Soluna registers a $471.8 million AI data center building with about 112 MW of critical IT load at Project Kati II in Willacy County, Texas

A Soluna entity registered Project Kati II with the Texas Department of Licensing and Regulation on October 7, 2026. The filing describes a single story, 471,884 square foot AI data center with a critical IT load of about 112 MW, an estimated cost of $471.8 million, and estimated construction from October 8, 2026 to October 8, 2027. No tenant is assigned. [Source 1]

Soluna registers a $471.8 million AI data center building with about 112 MW of critical IT load at Project Kati II in Willacy County, Texas
All news & analysisDevelopment & Power1392 FM 1420, Santa Monica area, Willacy County, TexasProposed. Registered with TDLR on October 7, 2026, status Project Registered, with estimated construction dates of October 8, 2026 to October 8, 2027. The registration does not confirm that construction has started. No tenant assigned. Not available. As of October 14, 2026.

Disclosed terms

Critical IT load
About 112 MW, per the TDLR scope of work [1]
Building
Single story, about 471,884 square feet [1]
Estimated cost
$471.8 million [1]
Estimated schedule
October 8, 2026 to October 8, 2027 [1]
Joint venture phases
Phase I 100 MW critical IT; Phase II additional 250 MW critical IT [2]

The disclosure and our analysis

Evidence dates

Evidence: TDLR project registration TABS2027003019, registered October 7, 2026 and read October 14, 2026; Soluna Form 8-K filed June 9, 2026 describing a June 3 joint venture agreement; Soluna second quarter release of August 13, 2026; Soluna release of September 8, 2026; Soluna and Metrobloks release of January 15, 2026.

What the filing shows

The registration names the project Project Kati II and the facility MFE-A-Kati2 Building 1, at 1392 FM 1420 in the Santa Monica area of Willacy County. The owner is Soluna KK Energy Service Co LLC of Albany, New York. The design firm is HKS, Inc. of Dallas. [Source 1]

The scope of work describes an AI data center with a critical IT load of about 112 MW in a single story building of about 471,884 square feet. The estimated cost is $471.8 million. The filing says the project is privately funded, on private land, for private use. It lists an estimated start of October 8, 2026 and estimated completion of October 8, 2027. The tenant field reads Not Assigned. [Source 1]

TDLR registration is an accessibility review filing. It is not a building permit and does not establish that construction has begun.

How this fits Soluna's disclosures

Soluna said in January it had signed a nonbinding memorandum with Metrobloks to co develop Project Kati 2, also called MB MFE-A, targeting an initial 100+ MW of critical IT for AI and high performance computing. [Source 5] On June 3, 2026, a Soluna subsidiary signed a joint venture agreement with a Metrobloks managed entity. Soluna's 8-K describes Phase I as a 100 MW critical IT data center development and Phase II as an additional 250 MW of critical IT. Soluna holds the Class A interests and manages the venture. After Soluna recovers its capital, a 14% IRR and $100,000 per gross PPA MW, further distributions split 50/50. [Source 2] Soluna's August release repeats the 100 MW and 250 MW phases. [Source 3]

Soluna's September 8 release described Kati 2 as a planned 83 MW phase for AI and high performance computing, alongside the energized 83 MW Kati 1 phase used for Bitcoin hosting. It did not state the power basis of that figure. [Source 4]

The sources use different figures: about 112 MW of critical IT in the TDLR filing, 100 MW of critical IT for Phase I in the joint venture filing, and 83 MW in the September release. We do not combine or reconcile them. The TDLR figure is the most recent and the only one tied to a single registered building.

Buyer analysis

This is our analysis.

**A real building filing, not yet a delivery date.** The registration gives a building size, cost, designer and a target completion of October 2027. Those are estimates on a state filing. Buyers should ask for the construction start, energization schedule and commissioning plan in writing.

**Power and curtailment terms matter here.** Kati is a wind powered campus. Soluna's September 8 release reported a conditional ERCOT Base Load classification for the full Kati campus. [Source 4] Buyers should confirm whether the AI building's power is grid backed, behind the meter or both, and what curtailment exposure applies.

**Not open inventory.** No tenant is assigned on the filing, but that does not mean capacity is available. Soluna has not published pricing or a leasing offer.

What remains unknown

The reviewed sources do not disclose a tenant, lease terms, pricing, the utility service capacity for the building, the interconnection status for the AI load, project financing, or whether site work has begun.

Sources

  1. Texas Department of Licensing and Regulation, TABS2027003019 · Published 2026-10-07
  2. Soluna Holdings, Form 8-K (joint venture agreement of June 3, 2026) · Published 2026-06-09
  3. Soluna Holdings, second quarter 2026 results release (SEC exhibit) · Published 2026-08-13
  4. Soluna Holdings, Kati 1 completion release (SEC exhibit) · Published 2026-09-08
  5. Soluna Holdings and Metrobloks release (SEC exhibit) · Published 2026-01-15

Related reporting

Development & Power

CleanSpark's 585 MW Sealy and Brazoria, Texas sites: tenant exclusivity expired, conditional ERCOT Batch Zero status

CleanSpark said on November 24, 2026 that the exclusivity period covering its Sealy and Brazoria, Texas campuses has expired, and that commercialization is proceeding with its existing Sandersville tenant and others. In the same fiscal fourth quarter release, the company reported a Conditional Batch Zero Baseload designation on 585 MW: 285 MW at Sealy and 300 MW at Brazoria Phase 1. It disclosed no Texas lease. [Source 1]

Sealy and Brazoria campuses, Texas · Announced sites with conditional grid designations (CleanSpark reports Conditional Batch Zero Baseload designation on 585 MW and Conditional Batch Zero Studied Load for Brazoria Phase 2, up to 300 MW, as of November 24, 2026). Tenant exclusivity expired. No lease disclosed. Not available capacity.
Read the analysis
Development & Power

Denton, Texas data center permit S26-0006 seeks a Specific Use Permit for 23.8 acres off E. University Dr.

A Specific Use Permit application for a data center on 23.8 acres in Denton, Texas, south of E. University Dr. and west of Geesling Rd., was submitted to the City of Denton on November 9, 2026. The city's planning record lists it as case S26-0006, project name Birddog, on land zoned Light Industrial and not platted. Its status was Under Review as of November 13, 2026. The record lists no megawatts, end user or hearing date. [Source 1]

South of E. University Dr. and west of Geesling Rd., Denton, Denton County, Texas · Proposed (Specific Use Permit application S26-0006 submitted November 9, 2026; city status Under Review as of November 13, 2026). No hearing date set in the record. No megawatt figure, tenant or end user disclosed.
Read the analysis
Development & Power

Entergy Arkansas plans a second phase of service for Google's West Memphis data center campus, with about $600 million of grid work and a 440 MW solar contract paid for by Google

Entergy Arkansas announced on October 19, 2026 a second phase of electric service for Google's data center campus in West Memphis, Arkansas. The utility says the phase needs about $600 million of planned investment plus a power purchase agreement, all covered by Google: two battery systems, a 440 MW (ac) solar contract, an expanded Galet substation and two new 230 kV lines to serve the expanded campus. The expansion still has to be submitted to the Arkansas Public Service Commission; Entergy targets service in 2028 if it is approved. Entergy listed the expanded Google agreement among its third quarter highlights on November 2. [Source 1] [Source 2]

West Memphis, Crittenden County, Arkansas · Announced October 19, 2026; to be submitted to the Arkansas Public Service Commission for approval. Pending approval, Entergy expects service in 2028. Not approved as of November 2, 2026.