Colocation Scout / News & Analysis

Applied Digital signs a 15-year power deal with a planned 1,200 MW gas plant for its Polaris Forge 3 campus, from a developer run by its own executives

Applied Digital disclosed in its quarterly report filed October 7, 2026 that on October 4 it signed a power purchase agreement and a credit support agreement with Base Electron for capacity and energy from an approximately 1,200 MW natural gas plant that Base Electron plans to develop in Center, North Dakota. The plant is intended to provide dedicated generation for Applied Digital's Polaris Forge 3 campus. The agreement has a 15-year delivery term with fixed monthly payments based on target contract capacity, and Base Electron may terminate it if the plant has not reached financial close by March 31, 2027. Base Electron is a related party: Applied Digital owns about 10%, and it is owned and managed in part by Applied Digital officers and directors, including CEO Wes Cummins. [Source 1] [Source 2]

Applied Digital signs a 15-year power deal with a planned 1,200 MW gas plant for its Polaris Forge 3 campus, from a developer run by its own executives
All news & analysisDevelopment & PowerCenter, Oliver County, North Dakota (Polaris Forge 3 and planned Base Electron plant)Signed. Power purchase agreement and credit support agreement entered October 4, 2026, disclosed October 7, 2026. The 1,200 MW gas plant is proposed and not yet financed; Base Electron may terminate if financial close does not occur by March 31, 2027. Polaris Forge 3 is under construction and leased, with initial ready for service anticipated in the second half of 2027. As of October 7, 2026.

Disclosed terms

Power purchase agreement
Capacity and energy from a planned approximately 1,200 MW gas plant in Center, North Dakota [1]
Term and payments
15-year delivery term; fixed monthly payments based on target contract capacity [1]
Termination right
Base Electron may terminate if financial close has not occurred by March 31, 2027 [1]
Related party
Applied Digital owns about 10%; Base Electron is owned and managed in part by Applied Digital officers and directors [1]
Lease book
About 1.41 GW of critical IT load leased across five campuses as of August 31, 2026 [2]
Polaris Forge 3 timing
Initial ready for service anticipated second half of 2027; full capacity second half of 2028 [1]

The disclosure and our analysis

Evidence dates

Evidence: Applied Digital Form 10-Q for the quarter ended August 31, 2026, filed October 7, 2026, and its fiscal first quarter 2027 earnings release furnished the same day. The power purchase agreement is dated October 4, 2026. Lease and capacity figures are as of August 31, 2026 unless another date is given.

What Applied Digital disclosed

**The power deal:** On October 4, 2026, Applied Digital entered into a power purchase agreement and a related credit support agreement with Base Electron for capacity and energy from an approximately 1,200 MW natural gas fired generation facility to be developed in Center, North Dakota. The company says the plant is intended to provide dedicated generation for its Polaris Forge 3 campus. [Source 1]

**Terms disclosed:** The agreement has a 15-year delivery term and provides for fixed monthly payments based on target contract capacity. Base Electron may terminate it if financial close for the facility has not occurred by March 31, 2027. The filing does not disclose the payment amount, the target contract capacity, the energy price or the terms of the credit support agreement. [Source 1]

**The 1,200 MW figure is generating capacity.** It describes the planned power plant. It is not data center load, critical IT load or leasable space. [Source 1]

**Related party:** Base Electron is an independent power producer formed to develop dedicated generation for high-density AI data center campuses. As of October 4, Applied Digital owned about 10% of it. Base Electron is owned and managed by certain Applied Digital officers and directors acting individually, including Wes Cummins, Mr. Zhang and Dr. Nottenburg, along with third parties. Mr. Cummins and Mr. Zhang serve as Base Electron's chief executive officer and its president and secretary. Applied Digital's board approved the agreements after review by a board committee for Base Electron related party transactions. [Source 1]

**Other exposure:** As of August 31, 2026, Applied Digital also held a related party demand promissory note from Base Electron of up to $100 million, with $58.5 million of principal outstanding. Applied Digital says it is not Base Electron's primary beneficiary and does not consolidate it. [Source 1]

Polaris Forge 3 and the wider lease book

Applied Digital says its two buildings at Polaris Forge 3, with an aggregate 300 MW of capacity, are under construction. The 10-Q does not state the basis of that figure. The company anticipates initial ready for service in the second half of calendar 2027 and full capacity in the second half of 2028. The earnings release says Polaris Forge 3 is leased to a tier-one investment grade hyperscaler, which it does not name. [Source 1] [Source 2]

As of August 31, 2026, Applied Digital says it has leases for about 1.41 GW of critical IT load across five campuses: Polaris Forge 1, 2 and 3 in North Dakota, Delta Forge 1 in Louisiana and Delta Forge 2 in Alabama. It says those leases represent about $36 billion of contracted revenue over their initial base terms, or about $86 billion if all renewal options are exercised. On October 1, Polaris Forge 1 reached 250 MW of critical IT load ready for service, and the company expects initial operations at Polaris Forge 2 in Harwood to bring delivered critical IT load across its North Dakota campuses to 300 MW by the end of calendar 2026. [Source 2]

The company also says it closed $1.59 billion of 7.000% senior secured notes due 2031, issued at par through a subsidiary, to fund the third 150 MW building at Polaris Forge 1 and repay a $300 million bridge facility. [Source 2]

Buyer analysis

This is our analysis.

**None of this is open capacity.** Applied Digital describes all five campuses as leased. Buyers looking for space in North Dakota should not read the power deal or the 1.41 GW figure as inventory.

**Dedicated generation is becoming part of the campus plan.** A fixed monthly capacity payment for 15 years means Applied Digital is committing to pay for a plant before it is financed or built. If the plant reaches financial close, the campus gets power that does not depend on the shared grid alone. If it does not close by March 31, 2027, Base Electron can walk away, and Polaris Forge 3's power plan would need another source.

**The related party structure deserves scrutiny.** The supplier is run by the buyer's own chief executive and other insiders. The board says a committee reviewed the deal. Tenants, lenders and counterparties evaluating Applied Digital campuses may want to understand how pricing was set and how conflicts are managed, because the payment terms are not disclosed.

**Watch the March 2027 deadline.** That date is the clearest public test of whether the plant moves from planned to financed.

What remains unknown

The reviewed sources do not disclose the PPA's monthly payment amount, target contract capacity, energy price or fuel arrangements, the credit support terms, the plant's construction schedule or permits, or how much of the plant's output Polaris Forge 3 needs. They do not name the Polaris Forge 3 tenant or state the power basis of the campus's 300 MW figure. The agreements themselves were not reviewed.

Sources

  1. Applied Digital Corp., Form 10-Q · Published 2026-10-07
  2. Applied Digital Corp., earnings release (Form 8-K Exhibit 99.1) · Published 2026-10-07

Related reporting

Development & Power

Denton, Texas data center permit S26-0006 seeks a Specific Use Permit for 23.8 acres off E. University Dr.

A Specific Use Permit application for a data center on 23.8 acres in Denton, Texas, south of E. University Dr. and west of Geesling Rd., was submitted to the City of Denton on November 9, 2026. The city's planning record lists it as case S26-0006, project name Birddog, on land zoned Light Industrial and not platted. Its status was Under Review as of November 13, 2026. The record lists no megawatts, end user or hearing date. [Source 1]

South of E. University Dr. and west of Geesling Rd., Denton, Denton County, Texas · Proposed (Specific Use Permit application S26-0006 submitted November 9, 2026; city status Under Review as of November 13, 2026). No hearing date set in the record. No megawatt figure, tenant or end user disclosed.
Read the analysis
Development & Power

Entergy Arkansas plans a second phase of service for Google's West Memphis data center campus, with about $600 million of grid work and a 440 MW solar contract paid for by Google

Entergy Arkansas announced on October 19, 2026 a second phase of electric service for Google's data center campus in West Memphis, Arkansas. The utility says the phase needs about $600 million of planned investment plus a power purchase agreement, all covered by Google: two battery systems, a 440 MW (ac) solar contract, an expanded Galet substation and two new 230 kV lines to serve the expanded campus. The expansion still has to be submitted to the Arkansas Public Service Commission; Entergy targets service in 2028 if it is approved. Entergy listed the expanded Google agreement among its third quarter highlights on November 2. [Source 1] [Source 2]

West Memphis, Crittenden County, Arkansas · Announced October 19, 2026; to be submitted to the Arkansas Public Service Commission for approval. Pending approval, Entergy expects service in 2028. Not approved as of November 2, 2026.
Read the analysis
Development & Power

San Antonio now requires a City Council vote on every new data center after a 9-2 code change

San Antonio City Council voted 9-2 on October 29, 2026 to pass data center regulations proposed by District 6 Councilmember Ric Galvan. The approach requires a Specific Use Authorization, a zoning approval voted on by council, for each new data center, rather than allowing data centers by right where they meet set standards. The mayor said the change ensures council can review each data center application. The final signed ordinance was not posted in the sources we reviewed. [Source 1] [Source 2] [Source 4]

San Antonio, Bexar County, Texas (city limits) · Approved: City Council passed the data center code change 9-2 on October 29, 2026. Final signed ordinance not reviewed.
Read the analysis