Colocation Scout / News & Analysis

Black Hills signs long-term agreements to power Google's planned Cheyenne data center with up to 590 MW of grid service and about 2.1 GW of contracted supply through a private microgrid

Black Hills Corp. disclosed on October 6, 2026 that it signed definitive agreements, effective September 30, to serve a planned Google data center in Cheyenne, Wyoming through 2048. Black Hills will provide up to 590 MW of grid-connected energy service and manage about 2.1 GW of Wyoming-based, third-party contracted resources through a privately managed microgrid. The company says the project is anticipated to be served by a total resource mix of 2.7 GW, including reserve margins. Energy service is planned to begin in late 2027 and ramp to peak load in 2030. Black Hills plans to invest $1.8 billion from 2027 to 2029 in 564 MW of new gas generation, and Google has advanced $399 million for long lead equipment. [Source 1]

Black Hills signs long-term agreements to power Google's planned Cheyenne data center with up to 590 MW of grid service and about 2.1 GW of contracted supply through a private microgrid
All news & analysisDevelopment & PowerCheyenne, WyomingSigned. Definitive power agreements effective September 30, 2026, disclosed October 6, 2026, with terms through 2048. Energy service planned for late 2027 with ramp to peak load in 2030. Data center planned; some generation and transmission approvals pending. As of October 6, 2026.

Disclosed terms

Grid-connected service
Up to 590 MW of energy service through company-owned generation and market energy [1]
Microgrid supply
About 2.1 GW of Wyoming-based, third-party contracted resources managed by Black Hills [1]
Total resource mix
2.7 GW including reserve margins; not data center load [1]
New generation
564 MW nameplate gas generation, $1.8 billion from 2027 to 2029 [1]
Timing
Energy service from late 2027, ramp to peak load in 2030 [1]
Term
Agreements effective September 30, 2026 with terms through 2048 [1]
Google advances
$399 million refundable, for long lead equipment, to be reimbursed by June 30, 2027 [1]

The disclosure and our analysis

Evidence dates

Evidence: Black Hills Corp. Form 8-K filed October 6, 2026, and its press release furnished as Exhibit 99.1, dated October 6, 2026. The agreements are effective September 30, 2026.

What Black Hills disclosed

Black Hills Corp. (NYSE: BKH) signed two agreements to serve a planned Google data center to be constructed in Cheyenne, Wyoming: a Large Power Contract Services Agreement and a Generation Facilities Agreement. Both run through 2048. [Source 1] [Source 2]

**Power supply structure:** Black Hills will provide up to 590 MW of grid-connected energy service. Of that, 564 MW (nameplate) comes from new natural gas generation that a non-regulated Black Hills affiliate will build and own at its existing Cheyenne Prairie Generating Station. The remaining 26 MW comes from market energy purchases and retail service under the company's industrial tariff. [Source 1]

**Microgrid:** Black Hills will also manage the output of about 2.1 GW of Wyoming-based, third-party contracted resources through a privately managed microgrid under its Large Power Contract Service tariff. The release does not name those resources or their owners. [Source 1]

**Total resource mix:** Black Hills says the project, excluding additional transmission expansion, is anticipated to be served by a total resource mix of 2.7 GW, including reserve margins. That is a supply figure with reserves built in. It is not the data center's load, and the release does not state the facility's peak load or critical IT load. [Source 1]

**Timing:** The data center is planned to begin taking energy service in late 2027 and ramp to the project's peak load in 2030. [Source 1]

**Capital and advances:** Black Hills plans to invest $1.8 billion between 2027 and 2029 in the new generation. Google has provided $399 million of refundable advances for long lead equipment under a generation reservation agreement, which Black Hills expects to reimburse by June 30, 2027. [Source 1]

**Cost protections:** Black Hills says the agreements are structured so Google bears all costs of serving the planned data center for the life of the project. The listed protections include cost pass-through mechanisms, full recovery of generation capital over the contract term, early termination provisions, and collateral and financial assurance requirements. These are the company's descriptions; the agreements themselves are not filed. [Source 1]

**Black Hills economics:** The company expects the project to provide about $150 million of net income in 2030 and about $2.4 billion of unlevered free cash flow through 2048, net of the $1.8 billion capital investment. Revenue includes a return on the generation investment and microgrid management fees based on a contracted minimum peak load that rises through the ramp period. [Source 1]

Approvals and filings

Black Hills lists these regulatory steps: the Robinson substation certificate of public convenience and necessity, approved May 2026; an industrial siting permit for the Cheyenne Prairie expansion, filed July 2026; an air quality permit for that expansion, approved August 2026; a Large Customer Transmission Cost Adjustment Mechanism, filed June 2026; a South Cheyenne Transmission Expansion certificate, filed September 2026; and a Wyoming transmission expansion certificate to be filed in the fourth quarter of 2026. The industrial siting permit and the transmission filings are not described as approved. [Source 1]

Buyer analysis

This is our analysis.

**This is a single-tenant power deal, not colocation supply.** Everything here is dedicated to one planned Google facility. None of the 590 MW, 2.1 GW or 2.7 GW is capacity that colocation buyers in Cheyenne can lease.

**The structure is the news.** A utility building and owning dedicated gas generation, while also running a private microgrid that pools third-party supply for a single customer, is a template other utilities in power-constrained markets may copy. The customer funds equipment up front and carries the cost risk for two decades.

**Watch Cheyenne's grid for everyone else.** Black Hills says existing customers are protected from cost shifting. Still, new transmission filings are pending, and the company says it sees other regional large load opportunities. Buyers evaluating Cheyenne should ask providers how their own utility service is secured, whether any new large load tariff or transmission charge applies to them, and what delivery dates their utility has confirmed in writing.

**Timelines are plans.** Service in late 2027 and peak load in 2030 depend on equipment delivery, construction and pending regulatory approvals that Black Hills names as risks.

What remains unknown

The reviewed sources do not disclose the data center's peak load or critical IT load, its exact site, its size or construction schedule, Google's energy rates or microgrid management fee levels, or the identity and fuel mix of the roughly 2.1 GW of third-party resources. The agreements are not filed. Google's own statement on the project was not reviewed for this draft. Pending items include the Cheyenne Prairie industrial siting permit and the transmission filings.

Sources

  1. Black Hills Corp., press release (Form 8-K Exhibit 99.1) · Published 2026-10-06
  2. Black Hills Corp., Form 8-K · Published 2026-10-06

Explore the market

Related reporting

Development & Power

Taylor, Texas approves an annexation agreement for the 664-acre Taylor Technology Campus, binding the data center and on-site power project to reclaimed water cooling and noise limits

The Taylor City Council voted unanimously on October 8, 2026 to approve a development agreement with Big Watt Digital and PowerHouse Data Centers that brings the 664-acre Taylor Technology Campus, formerly Project Mustang, into city limits, according to local news reports. The campus plan includes data center facilities and on-site power generation. Under the city's published terms, the developers must use closed loop cooling with reclaimed water, keep data centers and power generation at least 700 feet from the south property line, hold noise to the greater of 65 dBA or the pre-development level, and commit $28.2 million to community investments. The city projects $1.38 billion in gross tax revenue over 20 years and says the developers did not request tax abatements with this agreement. [Source 1] [Source 2] [Source 3]

Between FM 112 and U.S. 79, east of Taylor, Williamson County, Texas · Approved. Taylor City Council approved a development agreement for annexation and development conditions on October 8, 2026, as reported by KUT and CBS Austin. Not established: tenant, power capacity, construction or availability. As of October 9, 2026.
Read the analysis
Development & Power

Applied Digital signs a 15-year power deal with a planned 1,200 MW gas plant for its Polaris Forge 3 campus, from a developer run by its own executives

Applied Digital disclosed in its quarterly report filed October 7, 2026 that on October 4 it signed a power purchase agreement and a credit support agreement with Base Electron for capacity and energy from an approximately 1,200 MW natural gas plant that Base Electron plans to develop in Center, North Dakota. The plant is intended to provide dedicated generation for Applied Digital's Polaris Forge 3 campus. The agreement has a 15-year delivery term with fixed monthly payments based on target contract capacity, and Base Electron may terminate it if the plant has not reached financial close by March 31, 2027. Base Electron is a related party: Applied Digital owns about 10%, and it is owned and managed in part by Applied Digital officers and directors, including CEO Wes Cummins. [Source 1] [Source 2]

Center, Oliver County, North Dakota (Polaris Forge 3 and planned Base Electron plant) · Signed. Power purchase agreement and credit support agreement entered October 4, 2026, disclosed October 7, 2026. The 1,200 MW gas plant is proposed and not yet financed; Base Electron may terminate if financial close does not occur by March 31, 2027. Polaris Forge 3 is under construction and leased, with initial ready for service anticipated in the second half of 2027. As of October 7, 2026.
Read the analysis
Development & Power

Applied Digital says 250 MW of critical IT load is now ready for service at its fully leased Polaris Forge 1 campus in North Dakota, and secures access to up to 1 GW of potential power in Finland

Applied Digital said on October 2, 2026 that three more 25 MW data halls reached Ready for Service at Polaris Forge 1 in Ellendale, North Dakota. That completes Building 2 at 150 MW and brings the campus's fully operational critical IT load to 250 MW, of 400 MW contracted at full buildout. The campus is fully leased; Applied Digital previously disclosed CoreWeave as tenant for all 400 MW. On October 6, the company said it signed an agreement giving it access to up to 1 GW of potential power capacity in Finland, with initial power availability anticipated beginning in 2028. [Source 1] [Source 2] [Source 3]

Ellendale, North Dakota (Polaris Forge 1); Finland, site not disclosed · Polaris Forge 1: 250 MW of critical IT load described by the company as fully operational, including 75 MW reaching Ready for Service on October 2, 2026; 400 MW leased at full buildout. Finland: agreement for access to up to 1 GW of potential power capacity, initial availability anticipated from 2028; announced October 6, 2026. As of October 6, 2026.
Read the analysis