Taylor, Texas approves an annexation agreement for the 664-acre Taylor Technology Campus, binding the data center and on-site power project to reclaimed water cooling and noise limits

The Taylor City Council voted unanimously on October 8, 2026 to approve a development agreement with Big Watt Digital and PowerHouse Data Centers that brings the 664-acre Taylor Technology Campus, formerly Project Mustang, into city limits, according to local news reports. The campus plan includes data center facilities and on-site power generation. Under the city's published terms, the developers must use closed loop cooling with reclaimed water, keep data centers and power generation at least 700 feet from the south property line, hold noise to the greater of 65 dBA or the pre-development level, and commit $28.2 million to community investments. The city projects $1.38 billion in gross tax revenue over 20 years and says the developers did not request tax abatements with this agreement. [Source 1] [Source 2] [Source 3]

Taylor, Texas approves an annexation agreement for the 664-acre Taylor Technology Campus, binding the data center and on-site power project to reclaimed water cooling and noise limits
All news & analysisDevelopment & PowerBetween FM 112 and U.S. 79, east of Taylor, Williamson County, TexasApproved. Taylor City Council approved a development agreement for annexation and development conditions on October 8, 2026, as reported by KUT and CBS Austin. Not established: tenant, power capacity, construction or availability. As of October 9, 2026.

Disclosed terms

Site
664 acres; data center facilities and on-site power generation [1]
Cooling
Closed loop cooling using reclaimed water [1]
South setback
700 feet for data centers, power generation and battery storage [1]
Noise
Greater of 65 dBA or pre-development level [1]
Community payments
$28.2 million [1]
Council vote
Approved unanimously, October 8, 2026 (reported) [3]

The disclosure and our analysis

Evidence dates

Evidence: City of Taylor news release on the proposed development agreement, posted October 2, 2026. Council approval on October 8, 2026, as reported by KUT and CBS Austin on October 9, 2026. We did not review the signed agreement or official minutes.

What was approved

**The vote:** KUT and CBS Austin report that the council unanimously approved the agreement at its Thursday, October 8 meeting. CBS Austin reports the vote as 5 to 0. Without an agreement, the city says the land would remain in unincorporated Williamson County, where it has no zoning authority. [Source 2] [Source 3] [Source 1]

**The project:** The city describes Taylor Technology Campus as a 664-acre project that includes data center facilities and on-site power generation, developed by Big Watt Digital and PowerHouse Data Centers. The developers had withdrawn their earlier annexation and zoning application in September. [Source 1]

**Water:** The site must use a closed loop cooling system with reclaimed water. Potable water may not be used for filling HVAC systems or evaporative cooling except in limited cases the city lists, including a written emergency approval or a delay or interruption in the city's reclaimed water service. The developers will fund utility connections and wastewater improvements and withdraw their state wastewater discharge permit application. [Source 1]

**Setbacks and buffers:** Buildings must be at least 300 feet from the north, east and west property lines. Along the south line, data centers, power generation and battery storage must be at least 700 feet away, and accessory structures at least 500 feet. A buffer of at least 400 feet with landscaping and berms applies near FM 112. [Source 1]

**Noise, lighting and generators:** Noise may not exceed the greater of 65 dBA or the measured pre-development level at the property lines. Lighting must meet the city's dark skies rules. Backup generator testing is limited to weekdays from 8 a.m. to 5 p.m. [Source 1]

**Payments:** The developers commit $28.2 million, including $13 million to the city and about $12.7 million for Taylor ISD programs, scholarships and workforce training, plus nonprofit grants. [Source 1]

**Tax:** The city projects $1.38 billion in gross tax revenue over 20 years and says the developers are not asking for tax abatements with this agreement. The city separately posted a notice of consideration of a tax abatement agreement on the same day; we did not confirm whether it relates to this project. [Source 1]

Buyer analysis

This is our analysis.

**This is an approval of terms, not capacity.** The council approved a development agreement and annexation path. The reviewed city release gives no megawatt figure for IT load, utility service or on-site generation, and no tenant, construction start or delivery date. Treat the campus as approved for annexation under conditions, not as available or under construction.

**On-site generation is part of the plan.** The city's terms address power generation and battery storage siting and generator use. That signals a project designed to rely at least partly on its own power, which matters in ERCOT where large load interconnection timing is now a major schedule risk.

**The conditions are a template.** Reclaimed water cooling, 700 foot setbacks for power generation and a 65 dBA cap are concrete, enforceable terms. Buyers evaluating Austin area sites should expect similar conditions in other Central Texas negotiations and ask whether a site's design already meets them.

What remains unknown

The reviewed sources do not disclose the campus's IT load, utility service capacity or on-site generation capacity, its fuel type, tenants, construction timeline or delivery dates. We did not review the signed agreement, official minutes, or any remaining zoning steps. Some local reports cite a 500 MW full buildout figure; we did not find it in the city's release and do not rely on it.

Sources

  1. City of Taylor, news release · Published 2026-10-02
  2. KUT · Published 2026-10-09
  3. CBS Austin · Published 2026-10-09

Explore the market

Related reporting

Development & Power

Applied Digital signs a 15-year power deal with a planned 1,200 MW gas plant for its Polaris Forge 3 campus, from a developer run by its own executives

Applied Digital disclosed in its quarterly report filed October 7, 2026 that on October 4 it signed a power purchase agreement and a credit support agreement with Base Electron for capacity and energy from an approximately 1,200 MW natural gas plant that Base Electron plans to develop in Center, North Dakota. The plant is intended to provide dedicated generation for Applied Digital's Polaris Forge 3 campus. The agreement has a 15-year delivery term with fixed monthly payments based on target contract capacity, and Base Electron may terminate it if the plant has not reached financial close by March 31, 2027. Base Electron is a related party: Applied Digital owns about 10%, and it is owned and managed in part by Applied Digital officers and directors, including CEO Wes Cummins. [Source 1] [Source 2]

Center, Oliver County, North Dakota (Polaris Forge 3 and planned Base Electron plant) · Signed. Power purchase agreement and credit support agreement entered October 4, 2026, disclosed October 7, 2026. The 1,200 MW gas plant is proposed and not yet financed; Base Electron may terminate if financial close does not occur by March 31, 2027. Polaris Forge 3 is under construction and leased, with initial ready for service anticipated in the second half of 2027. As of October 7, 2026.
Read the analysis
Development & Power

Applied Digital says 250 MW of critical IT load is now ready for service at its fully leased Polaris Forge 1 campus in North Dakota, and secures access to up to 1 GW of potential power in Finland

Applied Digital said on October 2, 2026 that three more 25 MW data halls reached Ready for Service at Polaris Forge 1 in Ellendale, North Dakota. That completes Building 2 at 150 MW and brings the campus's fully operational critical IT load to 250 MW, of 400 MW contracted at full buildout. The campus is fully leased; Applied Digital previously disclosed CoreWeave as tenant for all 400 MW. On October 6, the company said it signed an agreement giving it access to up to 1 GW of potential power capacity in Finland, with initial power availability anticipated beginning in 2028. [Source 1] [Source 2] [Source 3]

Ellendale, North Dakota (Polaris Forge 1); Finland, site not disclosed · Polaris Forge 1: 250 MW of critical IT load described by the company as fully operational, including 75 MW reaching Ready for Service on October 2, 2026; 400 MW leased at full buildout. Finland: agreement for access to up to 1 GW of potential power capacity, initial availability anticipated from 2028; announced October 6, 2026. As of October 6, 2026.
Read the analysis
Development & Power

Black Hills signs long-term agreements to power Google's planned Cheyenne data center with up to 590 MW of grid service and about 2.1 GW of contracted supply through a private microgrid

Black Hills Corp. disclosed on October 6, 2026 that it signed definitive agreements, effective September 30, to serve a planned Google data center in Cheyenne, Wyoming through 2048. Black Hills will provide up to 590 MW of grid-connected energy service and manage about 2.1 GW of Wyoming-based, third-party contracted resources through a privately managed microgrid. The company says the project is anticipated to be served by a total resource mix of 2.7 GW, including reserve margins. Energy service is planned to begin in late 2027 and ramp to peak load in 2030. Black Hills plans to invest $1.8 billion from 2027 to 2029 in 564 MW of new gas generation, and Google has advanced $399 million for long lead equipment. [Source 1]

Cheyenne, Wyoming · Signed. Definitive power agreements effective September 30, 2026, disclosed October 6, 2026, with terms through 2048. Energy service planned for late 2027 with ramp to peak load in 2030. Data center planned; some generation and transmission approvals pending. As of October 6, 2026.
Read the analysis