FERC accepts PJM's 50 MW large load definition and registry but rejects its plan to connect new large loads ahead of new capacity

The Federal Energy Regulatory Commission on October 9, 2026 accepted two parts of PJM Interconnection's large load proposal: a definition of Large Load as 50 MW or more of cumulative peak load at a single electrical site, and a Large Load Registry, both effective October 12, 2026. It rejected the rest, including the Interim Resource Adequacy Service that would have let new large loads connect before matching new capacity in exchange for curtailment exposure. [Source 1]

FERC accepts PJM's 50 MW large load definition and registry but rejects its plan to connect new large loads ahead of new capacity
All news & analysisDevelopment & PowerPJM Interconnection regionApproved in part. FERC accepted the Large Load definition and Large Load Registry effective October 12, 2026 and directed a PJM compliance filing within 30 days. IRAS, the new capacity designation requirement, Bring Your Own New Capacity rules and the demand curve exclusion were rejected. As of October 9, 2026.

Disclosed terms

Large Load definition
50 MW or more of cumulative peak load at a single electrical site [1]
Effective date
October 12, 2026 for the definition and registry [1]
Compliance filing
Due within 30 days of October 9, 2026 [1]
Rejected
IRAS, new capacity designation, Bring Your Own New Capacity and demand curve exclusion [1]

The disclosure and our analysis

Evidence dates

Evidence: FERC Order Accepting Tariff Revisions in Part and Rejecting Tariff Revisions in Part, 197 FERC ¶ 61,019, Docket ER26-3515-000, issued October 9, 2026, read in full text from FERC eLibrary on October 14, 2026; Utility Dive report dated October 12, 2026.

What PJM asked for

PJM filed on August 13, 2026. It proposed six elements: a definition of Large Load; a Large Load Registry; a new Interim Resource Adequacy Service, or IRAS; a requirement that load serving entities serving New Large Load designate new capacity at least equal to that load's peak; rules for Bring Your Own New Capacity arrangements; and rules to exclude Eligible New Large Load from the capacity auction demand curve starting with the 2029/2030 delivery year. [Source 1]

PJM told FERC it will be short of capacity to meet its reliability requirement beginning in the 2027/2028 delivery year, particularly due to data center load growth and the pace of data center interconnection. PJM described IRAS as involving curtailments when resources are insufficient to meet demand in real time. PJM wanted IRAS in place on June 1, 2027. [Source 1]

What FERC decided

**Accepted.** FERC accepted the Large Load definition and the Large Load Registry, effective October 12, 2026 as PJM requested, and directed PJM to make a compliance filing within 30 days. FERC found these two elements severable from the rest of the filing. [Source 1]

**Rejected.** FERC rejected the remaining revisions. The order says IRAS and Bring Your Own New Capacity are either outside the Commission's authority or were not shown to be just and reasonable and not unduly discriminatory. It cites significant discrepancies between PJM's transmittal letter and its proposed tariff language. On IRAS, the order says the Federal Power Act leaves regulation of retail sales to the states. [Source 1]

Commissioner Rosner filed a concurring statement. [Source 1] Utility Dive reports that he said states should set curtailment priorities, and that a PJM spokesperson said PJM is reviewing the order. [Source 2]

What the definition and registry cover

PJM's accepted definition: end use customer load with cumulative peak load of 50 MW or greater at a single electrical site behind one or more points of interconnection. Affiliated load facilities within a one mile radius count as a single site. [Source 1] The 50 MW threshold is a peak load measure, not critical IT load, and it is not limited to data centers.

Load serving entities must report Large Loads they serve to PJM. PJM says the registry will include the customer, location, the in service date for each load increment, peak load and ramp schedule, the point of interconnection, telemetry, backup generation including fuel type and permit limits, and contracts between the load and its load serving entity. [Source 1]

Buyer analysis

This is our analysis, not a finding in the order.

**No fast lane for now.** IRAS would have offered new large loads a path to connect before new capacity existed, with curtailment risk attached. That path is rejected. Buyers planning capacity in PJM should not assume a federal interim service will shorten power timelines. Any curtailment framework now looks more likely to come through states or a revised PJM filing.

**More disclosure on power plans.** The registry asks for ramp schedules, interconnection points and backup generation details for every site of 50 MW or more. Providers in PJM will need this data in hand. Buyers can ask a provider for the same detail on their site's power ramp and backup generation.

**The capacity shortfall is PJM's statement.** PJM says it is short beginning in the 2027/2028 delivery year. The order does not resolve that shortfall.

What remains unknown

The reviewed sources do not show the content of PJM's compliance filing, whether or when PJM will refile IRAS or a revised version, how states will act on curtailment priorities, or any customer bill or capacity price effect.

Sources

  1. FERC, Order Accepting Tariff Revisions in Part and Rejecting Tariff Revisions in Part, PJM Interconnection, Docket ER26-3515-000, 197 FERC ¶ 61,019 · Published 2026-10-09
  2. Utility Dive, FERC rejects most of PJM's large load interconnection plan · Published 2026-10-12

Explore the market

Related reporting

Development & Power

CleanSpark's 585 MW Sealy and Brazoria, Texas sites: tenant exclusivity expired, conditional ERCOT Batch Zero status

CleanSpark said on November 24, 2026 that the exclusivity period covering its Sealy and Brazoria, Texas campuses has expired, and that commercialization is proceeding with its existing Sandersville tenant and others. In the same fiscal fourth quarter release, the company reported a Conditional Batch Zero Baseload designation on 585 MW: 285 MW at Sealy and 300 MW at Brazoria Phase 1. It disclosed no Texas lease. [Source 1]

Sealy and Brazoria campuses, Texas · Announced sites with conditional grid designations (CleanSpark reports Conditional Batch Zero Baseload designation on 585 MW and Conditional Batch Zero Studied Load for Brazoria Phase 2, up to 300 MW, as of November 24, 2026). Tenant exclusivity expired. No lease disclosed. Not available capacity.
Read the analysis
Development & Power

Denton, Texas data center permit S26-0006 seeks a Specific Use Permit for 23.8 acres off E. University Dr.

A Specific Use Permit application for a data center on 23.8 acres in Denton, Texas, south of E. University Dr. and west of Geesling Rd., was submitted to the City of Denton on November 9, 2026. The city's planning record lists it as case S26-0006, project name Birddog, on land zoned Light Industrial and not platted. Its status was Under Review as of November 13, 2026. The record lists no megawatts, end user or hearing date. [Source 1]

South of E. University Dr. and west of Geesling Rd., Denton, Denton County, Texas · Proposed (Specific Use Permit application S26-0006 submitted November 9, 2026; city status Under Review as of November 13, 2026). No hearing date set in the record. No megawatt figure, tenant or end user disclosed.
Read the analysis
Deals & Leasing

Amazon data centers in northern Indiana and Mississippi: Blackstone trust values 647 MW at $5.0B, a 7.0% cap rate

Blackstone Digital Infrastructure Trust (NYSE: BXDC) has agreed to buy a 75.1% controlling interest in two joint ventures that will own 13 newly constructed Amazon data centers with 647 megawatts of aggregate IT power capacity, nine buildings in northern Indiana and four in Mississippi, according to a Form 8-K filed November 16, 2026. The filing puts the aggregate gross value at $5.0 billion at an initial capitalization rate of 7.0%. At closing, Amazon Data Services will lease back 100% of both campuses on triple net leases with a weighted average initial term of 12 years and a 2.75% annual rent escalator. The deal had not closed as of the filing; either side may terminate if it does not close by December 31, 2026. [Source 1] [Source 2]

Northern Indiana (greater Chicago market) and Mississippi; exact sites not disclosed · Announced as of November 16, 2026: contribution agreement signed November 11, 2026, closing pending and expected in Q4 2026. To be 100% leased to Amazon Data Services at closing. Not available to other buyers.
Read the analysis