FERC accepts PJM's 50 MW large load definition and registry but rejects its plan to connect new large loads ahead of new capacity

The Federal Energy Regulatory Commission on October 9, 2026 accepted two parts of PJM Interconnection's large load proposal: a definition of Large Load as 50 MW or more of cumulative peak load at a single electrical site, and a Large Load Registry, both effective October 12, 2026. It rejected the rest, including the Interim Resource Adequacy Service that would have let new large loads connect before matching new capacity in exchange for curtailment exposure. [Source 1]

FERC accepts PJM's 50 MW large load definition and registry but rejects its plan to connect new large loads ahead of new capacity
All news & analysisDevelopment & PowerPJM Interconnection regionApproved in part. FERC accepted the Large Load definition and Large Load Registry effective October 12, 2026 and directed a PJM compliance filing within 30 days. IRAS, the new capacity designation requirement, Bring Your Own New Capacity rules and the demand curve exclusion were rejected. As of October 9, 2026.

Disclosed terms

Large Load definition
50 MW or more of cumulative peak load at a single electrical site [1]
Effective date
October 12, 2026 for the definition and registry [1]
Compliance filing
Due within 30 days of October 9, 2026 [1]
Rejected
IRAS, new capacity designation, Bring Your Own New Capacity and demand curve exclusion [1]

The disclosure and our analysis

Evidence dates

Evidence: FERC Order Accepting Tariff Revisions in Part and Rejecting Tariff Revisions in Part, 197 FERC ¶ 61,019, Docket ER26-3515-000, issued October 9, 2026, read in full text from FERC eLibrary on October 14, 2026; Utility Dive report dated October 12, 2026.

What PJM asked for

PJM filed on August 13, 2026. It proposed six elements: a definition of Large Load; a Large Load Registry; a new Interim Resource Adequacy Service, or IRAS; a requirement that load serving entities serving New Large Load designate new capacity at least equal to that load's peak; rules for Bring Your Own New Capacity arrangements; and rules to exclude Eligible New Large Load from the capacity auction demand curve starting with the 2029/2030 delivery year. [Source 1]

PJM told FERC it will be short of capacity to meet its reliability requirement beginning in the 2027/2028 delivery year, particularly due to data center load growth and the pace of data center interconnection. PJM described IRAS as involving curtailments when resources are insufficient to meet demand in real time. PJM wanted IRAS in place on June 1, 2027. [Source 1]

What FERC decided

**Accepted.** FERC accepted the Large Load definition and the Large Load Registry, effective October 12, 2026 as PJM requested, and directed PJM to make a compliance filing within 30 days. FERC found these two elements severable from the rest of the filing. [Source 1]

**Rejected.** FERC rejected the remaining revisions. The order says IRAS and Bring Your Own New Capacity are either outside the Commission's authority or were not shown to be just and reasonable and not unduly discriminatory. It cites significant discrepancies between PJM's transmittal letter and its proposed tariff language. On IRAS, the order says the Federal Power Act leaves regulation of retail sales to the states. [Source 1]

Commissioner Rosner filed a concurring statement. [Source 1] Utility Dive reports that he said states should set curtailment priorities, and that a PJM spokesperson said PJM is reviewing the order. [Source 2]

What the definition and registry cover

PJM's accepted definition: end use customer load with cumulative peak load of 50 MW or greater at a single electrical site behind one or more points of interconnection. Affiliated load facilities within a one mile radius count as a single site. [Source 1] The 50 MW threshold is a peak load measure, not critical IT load, and it is not limited to data centers.

Load serving entities must report Large Loads they serve to PJM. PJM says the registry will include the customer, location, the in service date for each load increment, peak load and ramp schedule, the point of interconnection, telemetry, backup generation including fuel type and permit limits, and contracts between the load and its load serving entity. [Source 1]

Buyer analysis

This is our analysis, not a finding in the order.

**No fast lane for now.** IRAS would have offered new large loads a path to connect before new capacity existed, with curtailment risk attached. That path is rejected. Buyers planning capacity in PJM should not assume a federal interim service will shorten power timelines. Any curtailment framework now looks more likely to come through states or a revised PJM filing.

**More disclosure on power plans.** The registry asks for ramp schedules, interconnection points and backup generation details for every site of 50 MW or more. Providers in PJM will need this data in hand. Buyers can ask a provider for the same detail on their site's power ramp and backup generation.

**The capacity shortfall is PJM's statement.** PJM says it is short beginning in the 2027/2028 delivery year. The order does not resolve that shortfall.

What remains unknown

The reviewed sources do not show the content of PJM's compliance filing, whether or when PJM will refile IRAS or a revised version, how states will act on curtailment priorities, or any customer bill or capacity price effect.

Sources

  1. FERC, Order Accepting Tariff Revisions in Part and Rejecting Tariff Revisions in Part, PJM Interconnection, Docket ER26-3515-000, 197 FERC ¶ 61,019 · Published 2026-10-09
  2. Utility Dive, FERC rejects most of PJM's large load interconnection plan · Published 2026-10-12

Explore the market

Related reporting

Development & Power

Stafford County, Virginia approves the Accokeek Center data center rezoning, with about 122 MW of Dominion service planned at full build-out

Stafford County supervisors voted 4-3 on October 7, 2026 to rezone about 121 acres for the Accokeek Center data center campus and to approve a Dominion substation permit, according to local reports. County documents describe up to 590,000 square feet in two buildings between U.S. 1 and Interstate 95. The applicant says the project is expected to need about 122 MW of electrical service at full build-out. [Source 1] [Source 3] [Source 4]

West side of Richmond Highway (U.S. 1), about 2,500 feet north of Eskimo Hill Road, Falmouth District, Stafford County, Virginia · Approved. Rezoning to M-2 and the substation conditional use permit approved 4-3 on October 7, 2026, per local reports; county minutes were not yet posted when checked on October 14, 2026. Site plan and utility approvals remain. The applicant's fiscal analysis expects the first building to operate in 2029. Not available. As of October 14, 2026.
Read the analysis
Development & Power

Soluna registers a $471.8 million AI data center building with about 112 MW of critical IT load at Project Kati II in Willacy County, Texas

A Soluna entity registered Project Kati II with the Texas Department of Licensing and Regulation on October 7, 2026. The filing describes a single story, 471,884 square foot AI data center with a critical IT load of about 112 MW, an estimated cost of $471.8 million, and estimated construction from October 8, 2026 to October 8, 2027. No tenant is assigned. [Source 1]

1392 FM 1420, Santa Monica area, Willacy County, Texas · Proposed. Registered with TDLR on October 7, 2026, status Project Registered, with estimated construction dates of October 8, 2026 to October 8, 2027. The registration does not confirm that construction has started. No tenant assigned. Not available. As of October 14, 2026.
Read the analysis
Development & Power

Cipher lifts its Barber Lake cost estimate to about $2.94 billion and plans an $850 million note sale that will help fund it

Cipher Digital now estimates that its Barber Lake data center in Colorado City, Texas will cost $2,941 million to $2,966 million to complete, against an original budget of $2,157 million, according to an investor presentation filed with the SEC on October 13, 2026. The cost estimate is dated October 6, 2026. The same filing shows two of the facility's five data halls with rent commencement moved from the fourth quarter of 2026 to the first quarter of 2027, and announces a proposed $850 million private offering of convertible notes whose proceeds will partly fund additional equity in the project. [Source 1] [Source 2]

Colorado City, Texas · Under construction. Cipher says construction is on track to meet amended delivery milestones, with rent commencement on Data Halls 1 and 2 in Q4 2026, Data Halls 3 and 4 in Q1 2027 (originally Q4 2026) and Data Hall 5 in Q1 2027. Leased to Fluidstack, with a follow-on AI lab commitment. Not available. As of September 30, 2026, with the cost estimate as of October 6, 2026.
Read the analysis