Google signs a 20-year deal to fund 890 MW of nuclear uprates at 11 Constellation units in PJM, plus a 15-year supply agreement for 2,700 MW of existing output

Google and Constellation Energy announced on October 6, 2026 a 20-year power purchase agreement that funds uprates at 11 Constellation nuclear units in Illinois, Pennsylvania and New Jersey, adding 890 MW of new generating capacity to the PJM grid. The first uprate is expected by 2028. The companies also signed a 15-year energy supply agreement covering an additional 2,700 MW of Constellation's existing PJM fleet. Constellation says the deal represents more than $4.3 billion of new investment. It is Constellation's second long-term nuclear agreement with a hyperscaler in a week, after Amazon's Calvert Cliffs deal on September 30. [Source 1] [Source 2]

Google signs a 20-year deal to fund 890 MW of nuclear uprates at 11 Constellation units in PJM, plus a 15-year supply agreement for 2,700 MW of existing output
All news & analysisDevelopment & PowerPJM Interconnection: Constellation nuclear sites in Illinois, Pennsylvania and New JerseyAnnounced. 20-year power purchase agreement for 890 MW of new nuclear generating capacity through uprates at 11 Constellation units; first uprate expected by 2028. Separate 15-year energy supply agreement covering 2,700 MW of existing PJM generation. As of October 6, 2026. No data center locations disclosed.

Disclosed terms

New nuclear capacity
890 MW of generating capacity through uprates at 11 Constellation units, first expected by 2028 [1]
Term
20-year power purchase agreement [1]
Existing fleet supply
15-year energy supply agreement for 2,700 MW of existing PJM generation [1]
Investment
More than $4.3 billion by Constellation, as stated by the companies [1]
Demand flexibility
Google load-shaping and demand response during high-stress grid events [1]
Amazon Calvert Cliffs deal
20 years, 690 MW including a 190 MW uprate due 2030 to 2032 [2]

The disclosure and our analysis

Evidence dates

Evidence: Constellation Energy and Google joint news release dated October 6, 2026; Constellation Energy and Amazon joint news release dated September 30, 2026.

What Google and Constellation disclosed

The 20-year power purchase agreement will fund new equipment and technology at 11 Constellation-owned nuclear units across six sites in Illinois, Pennsylvania and New Jersey. The companies say the work raises thermal and electrical efficiency and adds 890 MW of generating capacity that is "entirely new" to the PJM footprint. The first uprate is expected to be delivered by 2028. [Source 1]

Separately, the companies entered into a 15-year energy supply agreement for an additional 2,700 MW of Constellation's existing PJM fleet. The release calls this a financial structure that keeps those operating plants delivering energy and capacity to the PJM market. It does not describe the 2,700 MW as new capacity. [Source 1]

Constellation says the agreement represents more than $4.3 billion of new investment by Constellation, sustains about 4,400 existing jobs and creates about 7,200 construction jobs. [Source 1]

The release lists "demand flexibility integration" as a key element: Google incorporates operational load-shaping and demand-response capabilities to curtail non-critical power consumption during high-stress grid events. [Source 1]

The companies present the deal as a response to PJM's "Bring Your Own Power" proposal and say it aligns with the White House Ratepayer Protection Pledge. Google says it is bringing new capacity to PJM to support its growth without passing costs to residential customers. Those are the companies' characterizations. [Source 1]

Google and Constellation also agreed on a framework to evaluate new clean generation, storage and demand response projects, with near-term priority on PJM, and Constellation expanded a five-year technology agreement with Google Cloud and Gemini Enterprise. [Source 1]

The Amazon deal a week earlier

On September 30, 2026, Constellation and Amazon announced a 20-year agreement covering 690 MW of power from the Calvert Cliffs Clean Energy Center in Lusby, Maryland, including a 190 MW uprate expected to come online between 2030 and 2032. Constellation says the agreement enables more than $3 billion of investment at the 1,790 MW plant and supports relicensing it for another 20 years. The parties also signed a retail supply agreement for Amazon operations in the 13-state PJM market. All Calvert Cliffs output continues to flow to the PJM grid. [Source 2]

Buyer analysis

This is our analysis.

**This is generation, not data center capacity.** The 890 MW is new generating capacity at nuclear plants, measured at the plants. It is not critical IT load, utility service to any data center or leasable space. The 2,700 MW agreement covers existing generation and adds no new supply. Neither release names a Google data center served by the deal.

**Delivery is gradual.** Only the first uprate is dated, by 2028. The release does not give a schedule for the rest of the 890 MW. Amazon's 190 MW Calvert Cliffs uprate is dated 2030 to 2032. Buyers should not read either deal as near-term relief for PJM power constraints.

**Hyperscalers are paying for new supply up front.** Both deals fund generation that would not otherwise be built, in exchange for long-term offtake. That is becoming the price of large load growth in PJM. Colocation and wholesale buyers will not sign deals like these themselves, but their providers face the same pressure. Ask providers how their power for future phases is procured and whether any new capacity charges or supply commitments will be passed through.

**Demand flexibility is part of the bargain.** Google committed to curtail non-critical load during grid stress. Expect utilities and grid operators to ask more large users, including colocation tenants with flexible workloads, for similar terms. Check whether your contract allows a provider to curtail or shift load and on what notice.

What remains unknown

The reviewed sources do not disclose pricing for either Google agreement, which 11 units and six sites are involved, the uprate schedule after the first unit, how the energy is allocated to Google facilities, or the regulatory approvals required. Power uprates at US reactors generally require Nuclear Regulatory Commission license amendments, and the release does not discuss them. The Amazon release does not disclose pricing or which Amazon facilities the retail supply agreement serves.

Sources

  1. Constellation Energy and Google, joint news release · Published 2026-10-06
  2. Constellation Energy and Amazon, joint news release · Published 2026-09-30

Related reporting

Development & Power

TeraWulf doubles contracted utility power at its Muskie campus in eastern Kentucky to 1 GW and pulls the second 500 MW phase forward a year

TeraWulf said on October 5, 2026 that its subsidiary signed amended and restated agreements with Kentucky Power on October 1 that raise contracted power capacity at its Muskie Data Campus in eastern Kentucky from 500 MW to 1 GW. The second 500 MW phase moves from 2030 to 2029, subject to Kentucky Public Service Commission approval and Kentucky Power's construction schedule. The first 500 MW phase remains targeted to begin ramping in 2028. No tenant has been disclosed. [Source 1] [Source 2]

Grayson, Kentucky · Proposed AI and HPC campus. Contracted utility service increased to 1 GW under amended Kentucky Power agreements executed October 1, 2026. First 500 MW targeted to begin ramping in 2028; second 500 MW targeted for 2029, subject to Kentucky PSC approval. No tenant disclosed as of October 5, 2026.
Read the analysis
Development & Power

Skybox registers a $550 million fourth building at its Hutto campus near Austin with Texas regulators

A September 30, 2026 filing with the Texas Department of Licensing and Regulation registers Skybox Hutto 4, a $550 million core and shell data center building of about 846,300 square feet at 3399 County Road 132 in Hutto, Williamson County. Construction is listed from January 20, 2027 to October 30, 2028. No tenant is assigned. Skybox markets the campus as PowerCampus Austin, with 600 MW of total load from on-site Oncor substations. [Source 1] [Source 3]

3399 County Road 132, Hutto, Williamson County, Texas · Proposed (state accessibility registration filed September 30, 2026; listed construction January 2027 to October 2028). Not a building permit. No tenant assigned.
Read the analysis
Development & Power

Oracle plans to subscribe to part of Point Beach nuclear output through We Energies, taking on about $300 million in fuel costs; Wisconsin regulators must approve

Oracle and We Energies announced on October 2, 2026 that Oracle will subscribe to a portion of the power We Energies is required to buy from the Point Beach Nuclear Plant. We Energies says the deal is expected to save its other customers about $300 million in fuel costs. Oracle ties the commitment to Project Lighthouse, its data center development in Port Washington, Wisconsin. The arrangement needs Public Service Commission of Wisconsin approval, and We Energies says full details will be filed in the coming months. [Source 1] [Source 2]

Port Washington, Wisconsin (data center); Point Beach Nuclear Plant, Manitowoc County, Wisconsin · Announced October 2, 2026. Oracle's subscription to part of the Point Beach purchase power arrangement is proposed and subject to Public Service Commission of Wisconsin approval; full terms not yet filed.