3
sites in the Denver metro filed to add data center capacity, all in Aurora: QTS's DEN1 campus and two campus site plans, applications the city has not yet accepted. The only stated figure is QTS's 22.5 MW in DC1.
2.5M
square feet of data center campus space in two Aurora site plans, applications the city has not yet accepted.
6
towns adopted a data center moratorium, three around each metro, though none of the three Colorado Springs towns had a data center application pending.
Aurora, where every Denver metro filing to add data center capacity was made, was the one council to reject a pause, 6-5 on August 10 with the mayor breaking the tie.
Operating facilities on the map (30)
The small hollow grey dots are data centers listed in the public PeeringDB facility list, each linked to its record. Listings marked closed are left off. A listed building is in no count on this page.
| Operator | Facility | City | Record |
|---|---|---|---|
| 365 Data Centers | 365 Data Centers Aurora (CO1) | Aurora | peeringdb.com/fac/16128 |
| Centersquare | Centersquare Denver (DEN1) | Highlands Ranch | peeringdb.com/fac/2621 |
| Centersquare | Centersquare Denver (DEN2) | Englewood | peeringdb.com/fac/2623 |
| ColoradoColo | ColoradoColo - Lakewood (LKWD) | Lakewood | peeringdb.com/fac/14149 |
| CoreSite | CoreSite - Denver (DE1) | Denver | peeringdb.com/fac/389 |
| CoreSite | CoreSite - Denver (DE2) | Denver | peeringdb.com/fac/1229 |
| Data102 | Data102 - COS01 | Colorado Springs | peeringdb.com/fac/8223 |
| Data102 | Data102 - COS02 | Colorado Springs | peeringdb.com/fac/8224 |
| DataBank, Ltd. | DataBank Denver (DEN1) | Englewood | peeringdb.com/fac/2977 |
| DataBank, Ltd. | DataBank Denver (DEN2) | Centennial | peeringdb.com/fac/2198 |
| DataBank, Ltd. | DataBank Denver (DEN3) | Denver | peeringdb.com/fac/10920 |
| DataBank, Ltd. | DataBank Denver (DEN4) | Westminster | peeringdb.com/fac/10921 |
| DataBank, Ltd. | Databank Denver (DEN5) | Centennial | peeringdb.com/fac/16588 |
| EdgeConneX Inc. | EdgeConneX Denver (EDCDEN01) | Englewood | peeringdb.com/fac/1875 |
| Equinix, Inc. | Equinix DE1 - Denver | Englewood | peeringdb.com/fac/4443 |
| Equinix, Inc. | Equinix DE2 - Denver | Denver | peeringdb.com/fac/696 |
| Flexential Corp. | Flexential - Denver/Aurora (DEN03) | Aurora | peeringdb.com/fac/2438 |
| Flexential Corp. | Flexential - Denver/Centennial (DEN05) | Centennial | peeringdb.com/fac/2449 |
| Flexential Corp. | Flexential - Denver/Downtown (DEN02) | Denver | peeringdb.com/fac/2450 |
| Flexential Corp. | Flexential - Denver/Englewood (DEN11) | Englewood | peeringdb.com/fac/2439 |
| H5 Data Centers | H5 Data Centers Denver | Greenwood Village | peeringdb.com/fac/3071 |
| IPI Partners, LLC | 1500 Champa | Denver | peeringdb.com/fac/1440 |
| Iron Mountain Data Centers | Iron Mountain Data Center - Denver (DEN-1) | Denver | peeringdb.com/fac/1896 |
| Lumen Technologies Inc | Level(3) Denver | Denver | peeringdb.com/fac/1221 |
| Massive Networks | LSVL-CTC1 | Louisville | peeringdb.com/fac/13111 |
| OneNeck IT Solutions LLC | US Signal CO01 - Denver | Englewood | peeringdb.com/fac/12305 |
| Sungard Availability Services | Sungard AS Aurora | Aurora | peeringdb.com/fac/10865 |
| Sungard Availability Services | Sungard AS Thornton | Thornton | peeringdb.com/fac/11867 |
| T5 Data Centers | T5@Colorado Springs | Colorado Springs | peeringdb.com/fac/11932 |
| Zayo Group | Zayo Networks | Louisville | peeringdb.com/fac/1049 |
What happened this quarter
Three sites filed, all in Aurora
Three sites in the Denver metro filed to add data center capacity, all in Aurora. At QTS's DEN1 campus, DC1 filed a 22.5 MW fit-out of two data halls and matching 22.5 MW power work, neither issued by the end of September. Because work inside an already permitted data center counts only when its filing states added power, QTS's DC3 fit-out and build-out are left out, as is CoreSite's DE3 in Denver, whose four September permits for a "2nd story data center buildout" add cooling units and a chiller with no power figure. No new-building permit filing appears in the reviewed Denver metro records.
Two new campus plans were submitted in Aurora
Site plans totaling 2.5 million square feet were submitted to Aurora in the quarter and reported by the press before October 1 (Denver Gazette): 1,000,000 square feet on 500 acres at the Aerotropolis Logistics Center, between East 26th and 48th Avenues (26-2645716), its documents in the record submitted August 11, and TEL01's 1,542,300 square feet on 260 acres, placed by its case number near East 56th Avenue and E-470 (26-2657108). The city has not yet accepted either, and both records read October 12. In the portal, open Project List and search the project number. The mayor later said Trident "must be stopped" (Denver Gazette, news coverage).
Six towns paused. Aurora chose rules instead.
Six towns adopted a data center moratorium, three around each metro. In the Denver metro, Broomfield acted on July 7 (ordinance, Colorado Politics, news coverage), Commerce City on September 21 (ordinance) and Thornton on September 22 (ordinance). Around Colorado Springs, Woodland Park acted on July 16 (minutes), Monument on July 20 (draft minutes) and Palmer Lake on September 10 (draft minutes). Aurora rejected a moratorium 6-5 on August 10, the mayor breaking the tie (Denver7, news coverage), and voted 7-4 to ask staff for rules (CPR News). On September 28 it banned new evaporative cooling, unanimously as reported (Sentinel Colorado).
Colorado Springs: one new case, one long wait
Vineyards Research Park (city record, filed July 7) is Colorado Springs' one planning case this quarter. The city record describes two 110,000 square foot light industrial and office buildings, while the applicant describes a GPU test lab (Gazette, news coverage). The city approved it, and it was appealed on September 30 (appeal record). Project Taurus kept its approval with a 50 MW cap when the Planning Commission denied the appeals 6-2-1 on July 23 (minutes), but on September 17 the council postponed the final appeal to April 13, 2027 (council record).
The quarter's filings
| Site | Square feet | Estimated cost, as filed | MW, as filed |
|---|---|---|---|
| Denver metro | |||
| QTS DEN1, data center DC1Aurora. Two jobs in 1 existing building | $55 million | 22.5 MW† | |
| Data center project at Aerotropolis Logistics CenterAurora. Site plan, building count not stated | 1,000,000 | ||
| TEL01 Data Center CampusAurora. Site plan and plat, building count not stated | 1,542,300 | ||
| Denver metro total, 3 sites | 2,542,3002 of 3 sites | $55 million1 of 3 sites | |
| Colorado Springs | |||
| Vineyards Research ParkColorado Springs. 2 buildings | 220,000 | ||
Each site's figures add up what its records state, and an empty cell means they state none. Estimated cost, as filed, is the filers' own unverified figure, not total project spend. QTS's $55 million adds its fit-out ($19,250,000) and its ESB job ($35,750,000), each filed twice and added once. The two metros are never added together, and Colorado Springs, with one site, needs no total. †Each QTS job states 22.5 MW. The two may describe the same 22.5 MW, so they are not added, and no other record states megawatts.
Completed October 5, 2026. These figures are frozen, and any later correction is listed under Sources and revisions. A filing is not space anyone can lease.
Sites filing to add data center capacity, by quarter
What to watch
- October 6, 2026: Brighton's council takes up a 90-day pause after an eight-building campus rezoning request (Denver7, news coverage), and Arvada hears an 18-month moratorium (city recap).
- October 21 to 28, 2026: the Public Utilities Commission hears Xcel's large-load tariff for loads of 50 MW or more (Proceeding 26AL-0137E, dates in Decision C26-0467), suspended until January 8, 2027.
- April 13, 2027: Colorado Springs City Council hears the Project Taurus appeals, while the Vineyards appeal has no date yet.
The records
The quarter's filings, in detail (Denver metro 3, Colorado Springs 1)
QTS DEN1, data center DC1
- Location
- 1160 N Gun Club Rd, Aurora
- Operator named in the record
- QTS
- Power
- 22.5 MW, stated on each record
- Work, as filed
- "22.5MW TFO", described as "tenant build out for two data hall spaces. Build out will include installing data racks, conveyance equipment and build out for tenant storage"
- Second job, as filed
- "22.5MW ESB" (ESB is not spelled out in the record)
- Filing and status
- Building permit applications for a tenant improvement, an online building folder and a limited building permit for each job. None issued by September 30, 2026.
- Filed
- July 1, 2026 (both jobs), August 20 and 21, 2026 (limited building permits)
- Estimated cost, as filed
- $19,250,000 (fit-out), $35,750,000 (ESB)
- Records
- 26-2636052-000-00, 26-2648528-000-00, 26-2636081-000-00, 26-2648292-000-00
Data center project at Aerotropolis Logistics Center
- Location
- Aurora. No address on the record. Between East 26th and East 48th Avenues, reported (Denver Gazette)
- Developer
- Aerotropolis Industrial Development, reported (Denver Gazette). The record names no applicant.
- Size
- 1,000,000 square feet on 500 acres
- Work, as filed
- "Site plan for the construction of a multi-building data center campus totaling 1,000,000 SF on 500 acres"
- Filing and status
- Site plan application, case DA-2214-04. Submitted, not yet accepted for review by the city.
- Filed
- Documents submitted August 11, 2026. The record's application date reads October 12, 2026.
- Record
- 26-2645716, Aurora Citizen Portal, Project List, project 1994428
TEL01 Data Center Campus
- Location
- Aurora. No address on the record.
- Size
- 1,542,300 square feet on 260 acres
- Work, as filed
- "Site plan for a 1,542,300 SF data center campus with associated utilities, drainage and site improvements and a plat on 260 acres"
- Filing and status
- Site plan and plat application, case DA-1478-17. Submitted, not yet accepted for review by the city. No supporting documents posted.
- Filed
- Application number issued September 25, 2026, by the city's numbering. The record's application date reads October 12, 2026.
- Record
- 26-2657108, Aurora Citizen Portal, Project List, project 2005880
Vineyards Research Park
- Location
- 3819 Janitell Rd, Colorado Springs
- Owner of record
- ERCOR Janitell Road, LLC
- Applicant
- Classic Consulting
- Size
- Two 110,000 square foot buildings on 33.79 acres
- Work, as filed
- "Two 110,000 SF freestanding buildings for light industrial and office use with accessory outdoor storage"
- Applicant's description
- A GPU test lab, reported (Gazette)
- Filing and status
- Development plan, approved by the city. Appealed September 30, 2026, by Vineyard Holdings SB, LLC.
- Filed
- July 7, 2026
- Records
- DEPN-26-0087 (development plan), APPL-26-0010 (appeal)
Every project in the record, Q1 2025 to Q3 2026 (Denver metro 10, Colorado Springs 2)
| Quarter | First filed | Permit first issued | Where | The work | Type | Metro | Declared value | Public records |
|---|---|---|---|---|---|---|---|---|
| Q1 2025 | February 19, 2025 | Q3 2025 August 18, 2025 | Aurora: 1140 N GUN CLUB RD, Aurora, CO | DEN1-DC2 Data Center - New Building - Storage Warehouse And Guard Shack, Gating System | New building | Denver metro | $305 million | 25-2509129-000-00, 25-2513934-000-00 |
| Q1 2025 | February 21, 2025 | None on record | Thornton: no site address in the record | Washington Datacenter (Farren) / Comprehensive Plan Amendment, Zoning Amendment, and Conc... | Planning case | Denver metro | Not stated | {B5412A21-05FA-48D6-9B63-A6E65450349F} |
| Q1 2025 | March 19, 2025 | Q3 2026 July 28, 2026 | Aurora: 1100 N GUN CLUB RD, Aurora, CO | DEN1-DC3 Storage Use Building - Core And Shell | New building | Denver metro | $305 million | 25-2515310-000-00, 25-2519410-000-00 |
| Q3 2025 | August 25, 2025 | None on record | Aurora: 23001 E 48TH AVE, Aurora, CO | Trident Data Center At Windler - Site Plan | Planning case | Denver metro | Not stated | DA-1707-46 |
| Q1 2026 | March 12, 2026 | None on record | Colorado Springs: 1565 High Tech Way, Colorado Springs, CO 80907 | Project Taurus - Data Center Use In Existing Building | Planning case | Colorado Springs | Not stated | DEPN-26-0039 |
| Q1 2026 | March 24, 2026 | None on record | Aurora: 1140 N GUN CLUB RD, Aurora, CO | QTS DEN1 DC2, 60 MW Fit Out - Hot Aisle Containment Tenant Improvement | Data hall fit-out | Denver metro | $252 million | 26-2613720-000-00, 26-2614863-000-00 |
| Q2 2026 | April 15, 2026 | Q3 2026 July 6, 2026 | Aurora: 1160 N GUN CLUB RD, Aurora, CO | QTS DEN1 DC1 6 MW Tenant Improvement - Fit Out Data Hall Interior Remodel | Data hall fit-out | Denver metro | $41.1 million | 26-2618176-000-00, 26-2618196-000-00, 26-2629045-000-00, 26-2629108-000-00 |
| Q3 2026 | July 1, 2026 | None on record | Aurora: 1160 N GUN CLUB RD, Aurora, CO | QTS DEN1 DC1, 22.5 MW TFO | Data hall fit-out | Denver metro | $19.3 million | 26-2636052-000-00, 26-2648528-000-00 |
| Q3 2026 | July 1, 2026 | None on record | Aurora: 1160 N GUN CLUB RD, Aurora, CO | QTS DEN1 DC1, 22.5 MW ESB | Data center power or cooling | Denver metro | $35.8 million | 26-2636081-000-00, 26-2648292-000-00 |
| Q3 2026 | July 7, 2026 | None on record | Colorado Springs: 3819 Janitell Rd, Colorado Springs, CO 80906 | Vineyards Research Park - New Development Plan | Planning case | Colorado Springs | Not stated | DEPN-26-0087 |
| Q3 2026 | August 11, 2026 | None on record | Aurora: no site address in the record | Data Center Project at Aerotropolis Logistics Center - Site Plan | Planning case | Denver metro | Not stated | 26-2645716 |
| Q3 2026 | September 25, 2026 | None on record | Aurora: no site address in the record | TEL01 Data Center Campus - Site Plan and Plat | Planning case | Denver metro | Not stated | 26-2657108 |
Where two records differ in value, the larger is shown.
State air permits, 2025 to 2026 (none in Q3 2026)
| Date | Facility, as the state names it | What happened | Permit |
|---|---|---|---|
| February 23, 2026 | Edgeconnex, Inc - Denver Campus | Construction permit issued | 25DG0038 |
| January 30, 2026 | Flexential - Den03 Data Center | Application received | 26AR0257 |
| November 17, 2025 | Amazon Data Services - Den-22 | Application received | 19AR0178 |
| July 17, 2025 | Coresite Real Estate DE3 - Coresite DE3 | Construction permit issued | 24DE0836 |
| July 8, 2025 | Quality Technology Services - QTS DEN1 | Modification application received | 22AR0210 |
| May 16, 2025 | Edgeconnex, Inc - Denver Campus | Application received | 25DG0038 |
| March 7, 2025 | Quality Technology Services - QTS DEN1 | Construction permit issued | 22AR0210 |
Colorado Air Pollution Control Division documents for data centers in the eight counties, from the state's public records system. None fall in Q3 2026. A generator permit rating is backup plant, not the capacity a customer can use, so no rating is shown as megawatts of space. If a state link has expired, search the permit number at the Colorado records portal.
Government actions, 2026
- Denver City Council: one-year moratorium on data center zoning and site plans (26-0431).
- Jefferson County: 10-month moratorium (county notice).
- Broomfield: Ordinance 2313, 18 months, unanimous as reported (Colorado Politics).
- Woodland Park: Ordinance 1525, 18 months, 7-0 (minutes).
- Monument: Ordinance 18-2026, six months, 6-0 (draft minutes).
- Colorado Springs Planning Commission: Project Taurus appeals denied 6-2-1, utility use capped at 50 MW (minutes).
- Aurora City Council: moratorium rejected 6-5 (Denver7), resolution to draft regulations adopted 7-4 (CPR News), as reported.
- Douglas County: 35-year property tax rebate for Flexential's Parker data center, unanimous (county release).
- Colorado Springs City Council: Buckingham Drive rezoning conditioned to bar data centers, Ordinance 26-38 (record).
- Palmer Lake: Resolution 31-2026, temporary moratorium, 4-0 (draft minutes).
- Colorado Springs City Council: Project Taurus appeal hearing postponed April 7-2 to 13, 2027 (record).
- Commerce City: six-month moratorium, 7-1 as reported (Westword).
- Thornton: 12-month moratorium on data centers over 50,000 square feet, 5-3 as reported (BusinessDen).
- Aurora City Council: evaporative cooling ban, final reading, unanimous as reported (Sentinel Colorado), first reading September 14 (Denver Gazette).
Reported (Denver metro 6, Colorado Springs 2)
Press reports, and records silent on what they build. None of these is in the counts above.
- Microsoft, Aurora. About 260 acres near East 56th Avenue and E-470, bought in 2022 (BusinessDen). No record links it to the TEL01 campus.
- NTT Global Data Centers, Aurora. 300,000 square feet under a 2025 incentive agreement, as reported (Sentinel Colorado). No application filed.
- Eight-building campus, Brighton. Rezoning confirmed by the city (Denver7). The site may lie in Weld County, outside the boundary.
- CoreSite DE3, Denver. A second- and third-story data center build-out with new cooling (city record). No power figure. QTS DEN1's DC3 fit-out (city record) and build-out (city record) state none either.
- Centersquare DEN2, Douglas County. A chiller, generator and IT equipment plan (county record) and a $34 million tenant finish (county record) at an operating data center. Neither states a power figure.
- Earlier build-outs with no power figure. QTS DEN1 DC2's six white boxes, 2025 (city record). 12396 Grant St, Thornton, 2025, expired unissued (city record). Each is inside an existing data center and states no added power.
- Novva, 650 Sybilla Lane, Colorado Springs. Growth to 30 MW, announced in 2021 (DCD). No application for new space found.
- Utility power requests, Colorado Springs, reported by the Pikes Peak Bulletin. 12710 Voyager Parkway: 50 MW. 1575 West Garden of the Gods Road, on the Project Taurus campus: 90 MW. Peak Innovation Park and the airport area: four requests, 60 to 500 MW. An existing customer: 72 MW. Operators and filings unconfirmed.
Coverage and method
Boundary. Denver metro: Denver, Arapahoe, Adams, Douglas, Jefferson and Broomfield counties. Boulder and Weld counties are separate metropolitan areas, and Lochbuie is outside. Colorado Springs: El Paso and Teller counties.
Records read. Denver metro: Aurora's building permits, development cases and development portal project list, by data center wording and QTS, plus Denver, Douglas County, Thornton, Centennial and unincorporated Adams County permits and planning records at known data center addresses or by wording, all partial. Jefferson County, Littleton, Westminster, Lakewood and Lone Tree show no data center case since 2025, and Parker, Brighton, Commerce City, Broomfield, Castle Rock, Englewood, Greenwood Village and unincorporated Arapahoe were not collected. Colorado Springs: planning cases and City Council, Planning Commission and Utilities Board records by wording and at known addresses, but not regional building department permits. No applications were identified in the other El Paso and Teller towns. Moratorium records: Denver, Jefferson County, Broomfield, Commerce City, Thornton, Monument, Palmer Lake, Woodland Park. State: Air Pollution Control Division generator permits for data centers in the eight counties, listed separately, and the Public Utilities Commission's large-load tariff case. The chart spans Q1 2025 to Q3 2026. Denver pagination and Centennial completed-permit histories extend coverage, but search limits and unknown aliases can leave earlier quarters undercounted.
What the figures include. Only filings that add data center buildings or capacity: new buildings and the jobs filed for them, planning cases for new data center sites, and, inside a data center already permitted, work whose filing states added power with a figure. Cooling or build-out work there with no power figure does not count, nor do replacements, repairs, renovations, fire and life-safety work, renewals, amendments or QTS's 3 MW liquid-cooling conversion, which converts a hall already in use. Aurora's two 2026 site plans not yet accepted count as planning cases: both were reported in the city portal before October 1. Aerotropolis is dated August 11, the submission date on its documents in the record, while TEL01, with none, is dated September 25 by its application number, which the city issues in one sequence with its permits. Each record reads an application date of October 12. A site, one address or one campus, counts once in any quarter in which it files, however many permits, and a project, one piece of work, is dated by its first filing however many records it has.
Certificates of occupancy. One since January 2025 at a data center address in the record: Denver's temporary certificate for the CoreSite DE3 building, 2026-OCCUPANCY-0000577, finaled August 13, 2026, a month before its data center build-out permits were filed. A certificate marks a building finished, never capacity available.
Sources and revisions
News coverage is named as news. Once final, this edition's figures are frozen, and any later correction is added here with its date and reason.
Colocation Scout is run by a wholesale and colocation consulting company. The permit data is public and every row links to its filing. How we publish these reports.
Revisions: Correction: on October 5, 2026, the Denver metro Q3 figure changed from 1 to 3 sites when the two Aurora site plan applications were added. The historical coverage description was clarified on October 6, 2026, to reflect recovered Denver and Centennial records. Quarterly figures did not change. Edition status: final.
Cite this report as: Colocation Scout, "Denver metro and Colorado Springs data center permits, Q3 2026," colocationscout.com/reports/denver-colorado-springs-data-center-permits-q3-2026.html