1
site filed to add data center capacity: a gas plant of up to about 430 MW for EdgeConneX's New Albany North site, applied for with the state on 24 July.
2,530
megawatts, at most, of gas plants for data centers awaiting a state decision at the quarter's end: two for EdgeConneX, at New Albany and Ashville, and the Fairfield Energy Center at Millersport.
12
local bodies voted on data centers, seven to limit them: two moratoria, a district ban in Dublin, and four bans or public-vote rules sent to voters.
The quarter's one new filing was a gas plant for EdgeConneX in New Albany, one of three data center plants waiting on the state, while Pataskala turned Aligned Data Centers down and seven of twelve local votes set limits.
Operating facilities on the map (21)
The small hollow grey dots are data centers operating today, from the public PeeringDB facility list, each linked to its PeeringDB record. An operating building is context for the filings and is in no count on this page.
| Operator | Facility | City | Record |
|---|---|---|---|
| Bresco Broadband | Bresco Broadband Data Center | Columbus | peeringdb.com/fac/3890 |
| Bresco Broadband | Continental Plaza | Columbus | peeringdb.com/fac/3891 |
| Centersquare | Centersquare Columbus (CMH1) | Lewis Center | peeringdb.com/fac/2594 |
| CENTRA Digital Interconnect | CENTRA CMH01 - Columbus Ohio (180 E Broad) | Columbus | peeringdb.com/fac/12210 |
| City of Westerville | WēConnect Westerville | Westerville | peeringdb.com/fac/7142 |
| Citynet | Citynet Columbus | Columbus | peeringdb.com/fac/267 |
| Cogent Communications, Inc. | Cogent Columbus | Columbus | peeringdb.com/fac/10479 |
| Cogent Communications, Inc. | Cogent Columbus 2 | Columbus | peeringdb.com/fac/16457 |
| Cologix, Inc. | Cologix COL1 | Columbus | peeringdb.com/fac/2377 |
| Cologix, Inc. | Cologix COL2 | Columbus | peeringdb.com/fac/2378 |
| Cologix, Inc. | Cologix COL3 | Columbus | peeringdb.com/fac/3313 |
| Cologix, Inc. | Cologix COL4 | Columbus | peeringdb.com/fac/14565 |
| Crown Castle Inc. | Crown Castle Columbus (101 E Town) | Columbus | peeringdb.com/fac/3493 |
| DartPoints, LLC | DartPoints Dublin, OH - CMH1 | Dublin | peeringdb.com/fac/9390 |
| DataCenter.BZ, LLC | Datacenter.BZ | Columbus | peeringdb.com/fac/1420 |
| DataCenter.BZ, LLC | DataCenter.BZ - Worthington-Columbus | Worthington | peeringdb.com/fac/1328 |
| Expedient | Expedient Columbus - Dublin | Dublin | peeringdb.com/fac/8471 |
| Expedient | Expedient Columbus - Upper Arlington | Upper Arlington | peeringdb.com/fac/8472 |
| Hexion Building | 180 E Broad St. | Columbus | peeringdb.com/fac/525 |
| Racksquared | Racksquared Data Centers | Columbus | peeringdb.com/fac/7609 |
| WideOpenWest Finance | WOW! Business (Columbus Datacenter) | Columbus | peeringdb.com/fac/1828 |
What happened this quarter
The one new filing is a power plant
One site filed to add data center capacity this quarter, and the filing was for power rather than a building. On 24 July PowerConneX, an EdgeConneX affiliate, applied to the Ohio Power Siting Board for a gas plant on EdgeConneX's New Albany North site on Clover Valley Road, which EdgeConneX describes as up to about 430 MW and the primary source of electricity for the data centers there. The board found the application complete on 4 September and set hearings for 22 October and 4 November. The power would come from on-site gas engines: Ohio EPA's draft air permit of 6 August, for "a data center and power generation facility" at the site, covers 30 of them. No new data center building was filed in the covered records, but those records leave out building permits in Licking and Union counties, where most of the market's campuses sit, because they cannot be searched online.
Pataskala said no to Aligned, and Ohio permitted the generators Aligned had already applied for
Pataskala's council voted 7-0 on 25 August to disapprove Aligned Data Centers' plan for three data center buildings on 89.41 acres at Broad and Mink streets. The generators are part of the same project, not a fallback from it. Aligned applied to Ohio EPA on 29 July, before the vote, for 129 emergency generators at 6770 Mink Street, and the state issued the permit six days after the vote. An air permit settles air quality, not local land use, so it does not revive the plan the council turned down. Pataskala's voters decide on 3 November whether to write a ban on data centers drawing more than 25 MW into the city charter. Aligned's case is not in the count because its records do not show when it was filed.
Twelve local bodies voted, and seven of them set limits on data centers
Set limits
Dublin, New Albany, Sunbury, Prairie Township, Pataskala, Plain City, Grove City
Both ways
Johnstown: a ban sent to a January vote, and a wider tax abatement area
The other way
Regional planners: plats extended for three Jerome Township campuses
Neither
Columbus peak rates, Marysville conditional use, Heath petitions rejected
Columbus and the state turn to the cost of power
Columbus's council voted 9-0 on 28 September to have its water and power department propose peak rates for large users, data centers named among them, by 26 October. On 5 August the Public Utilities Commission of Ohio ruled that a data center returning to AEP Ohio's standard service must give 180 days' notice and bear the cost of buying its power. Two gas plants filed earlier in the year, PowerConneX's plant of up to 800 MW at Ashville for EdgeConneX and the 1,300 MW Fairfield Energy Center at Millersport, went through hearings with no decision by the quarter's end. With New Albany North, that is up to 2,530 MW of gas plants for data centers waiting on the board.
The quarter's filings
PowerConneX New Albany 3, for EdgeConneX New Albany North
- Location
- 3356 Clover Valley Road NW, New Albany, Licking County, on about 30 acres
- Applicant of record
- PowerConneX, Inc., an EdgeConneX affiliate
- Power, as stated
- Up to about 430 MW, as EdgeConneX states it (EdgeConneX)
- Work, as described
- Gas-fired equipment "that will serve as a primary source of electricity to data centers on the same site"
- Filing and status
- Application for a certificate from the Ohio Power Siting Board, found complete on 4 September 2026. Hearings on 22 October and 4 November. No decision.
- Filed
- 24 July 2026
- Record
- 26-0361-EL-BGN
- Related state record
- Ohio EPA draft air permit P0140005 for EdgeConneX New Albany North, 6 August 2026 (draft permit)
Completed 8 October 2026. These figures are frozen, and any later correction is listed under Sources and revisions. Building permits in Licking and Union counties and Hilliard are not in the record, and a filing is not space anyone can lease.
Sites filing to add data center capacity, by quarter
What to watch
- By 26 October 2026: Columbus Water and Power owes council its proposed peak rates for large users, under Ordinance 2560-2026.
- 3 November 2026: voters in Pataskala and Sunbury decide charter bans on data centers over 25 MW, and Grove City voters decide whether large projects need a public vote (minutes).
- 4 November 2026: the siting board's evidentiary hearing on the New Albany North plant opens, after a local hearing on 22 October (docket).
The records
Every project in the record, Q1 2025 to Q3 2026 (18)
| First filed | Permit first issued | Where | The work | Type | Declared value | Record |
|---|---|---|---|---|---|---|
| 7 March 2025 | Board approval, Q2 2025 9 June 2025 | 14250 Morse Rd, New Albany | Gas plant for the data center of Sidecat, a Meta affiliate | Power plant, 200 MW | Not stated | 25-0185-EL-BLN |
| 26 March 2025 | None on record | 225 Rathmell Rd, Columbus | Site plan to add a data center | Site plan for a new data center | Not stated | 25345-00215 |
| 17 April 2025 | Q4 2025 22 December 2025 | 8510 Warner Rd, Jerome Township | Five data center buildings, 965,250 square feet | Five new buildings | Not stated | ZC 10827 |
| 17 April 2025 | Q4 2025 22 December 2025 | 7321 Industrial Pkwy, Jerome Township | Six data center buildings, 1,380,375 square feet | Six new buildings | Not stated | ZC 10826 |
| 23 April 2025 | Board approval, Q3 2025 24 July 2025 | 9850 Innovation Campus Way, New Albany | Gas plant for EdgeConneX's data center | Power plant, 120 MW | Not stated | 25-0090-EL-BLN |
| 25 April 2025 | Board approval, Q3 2025 18 September 2025 | 13385 Green Chapel Rd NW, New Albany | Gas plant for Sidecat's data center | Power plant, 200 MW | Not stated | 25-0188-EL-BGN |
| 8 May 2025 | Q3 2025 2 July 2025 | 225 Rathmell Rd, Columbus | Shell of a 288,000 square foot data center building | New building | $20 million shell, $200 million second phase | NEWC2516788, ALTC2530787 |
| 12 June 2025 | Q3 2025 11 September 2025 | 225 Rathmell Rd, Columbus | Two buildings to support server operations | Two new buildings | $100 million each | 25345-00443, NEWC2526040, NEWC2526056 |
| 24 June 2025 | Board approval, Q3 2025 22 September 2025 | 4186 Scioto Darby Creek Rd, Hilliard | AEP Ohio fuel cells for Amazon's data center campus | Fuel cells, 72.9 MW | Not stated | 25-0649-EL-BLN |
| 25 June 2025 | Board approval, Q4 2025 20 November 2025 | 9850 Innovation Campus Way, New Albany | Gas plant for EdgeConneX's data center | Power plant, 216 MW | Not stated | 25-0302-EL-BGN |
| 21 August 2025 | Q3 2025 19 September 2025 | 8575 Industrial Pkwy, Jerome Township | Data building of 192,746 square feet | New building | Not stated | ZC 11099 |
| 26 August 2025 | None on record | 225 Rathmell Rd, Columbus | Site plan to add a data center | Site plan for a new data center | Not stated | 25345-00641 |
| 17 November 2025 | Planning case, approved 15 December 2025 | Souder Rd, north of New Albany Rd E, New Albany | Data center of 330,000 square feet | Final development plan | Not stated | FDP-96-2025 |
| 25 November 2025 | Q4 2025 23 December 2025 | Industrial Pkwy, west campus, Jerome Township | First building of 214,300 square feet | New building | Not stated | ZC 11318, ZC 11358 |
| 27 March 2026 | Board approval, Q2 2026 26 June 2026 | 3439 Clover Valley Rd, New Albany | Gas plant for Sidecat's data center | Power plant, 250 MW | Not stated | 26-0169-EL-BLN |
| 1 April 2026 | Planning case, no decision on record | Rickenbacker Exchange extension, Commercial Point | Major site plan for a data center | Major site plan | Not stated | K-Nova II major site plan |
| 12 May 2026 | No board decision yet | State Route 752, Ashville | Gas plant for EdgeConneX's data center | Power plant, up to 800 MW | Not stated | 26-0196-EL-BGN |
| 24 July 2026 | No board decision yet | 3356 Clover Valley Rd NW, New Albany | Gas plant for EdgeConneX's New Albany North data centers | Power plant, up to about 430 MW | Not stated | 26-0361-EL-BGN |
Two series, never added together: City of Columbus permits and site plans, Jerome Township zoning certificates and dated planning cases, and power plant applications to the Ohio Power Siting Board, dated by the application. A declared value is the filer's own estimate and is never added to another.
State air permits for new data centers and their power plants (11)
| Date | Facility, as the state names it | Where | What happened | Permit |
|---|---|---|---|---|
| 22 September 2026 | STY power plant, Will-Power OH | New Albany | Draft permit | P0139969 |
| 31 August 2026 | Aligned Data Centers CMH01, 129 emergency generators | Pataskala | Permit issued | P0140511 |
| 6 August 2026 | EdgeConneX New Albany North, 30 gas engines | New Albany | Draft permit | P0140005 |
| 2 June 2026 | CMH170 Campus, 58 emergency generators | Marysville | Permit issued | P0140211 |
| 10 February 2026 | CMH098 Campus, 388 emergency generators | Johnstown | Permit issued | P0139005 |
| 10 February 2026 | Montauk Innovations, 47 emergency generators | New Albany | Permit issued | P0139081 |
| 16 December 2025 | Vantage OH2, 617 emergency generators | Millersport | Permit issued | P0138518 |
| 10 December 2025 | Cologix COL5, 15 generators | Orange Township | Permit issued | P0138685 |
| 18 November 2025 | CyrusOne New Albany, 145 emergency generators | New Albany | Permit issued | P0138459 |
| 8 October 2025 | AEP Ohio fuel cells, 72.91 MW | Hilliard | Permit issued | P0138549 |
| 29 July 2025 | CMH116 Campus, 303 emergency generators | Johnstown | Permit issued | P0137625 |
Ohio EPA permits for the generators and power plants of new data centers. 3 fall in Q3 2026. They are listed, not counted, because the records show when a permit was drafted or issued, not when it was applied for. A generator rating is backup plant, not capacity a customer can use.
Government actions, 2026 (17)
- Dublin council: Data centers dropped as a use in the West Innovation District, 6-1 (action summary).
- New Albany council: Data centers barred as a primary use on 22.6 rezoned acres, 7-0 (minutes).
- Marysville planning commission: Data centers made a conditional use in Marysville East, 7-0, a recommendation (minutes).
- Sunbury council: Charter ban on data centers over 25 MW sent to the ballot (ordinance).
- Prairie Township trustees: Moratorium extended to 15 April 2027, 3-0 (minutes).
- Pataskala council: Charter ban on data centers over 25 MW sent to the ballot, 4-0 (ordinance).
- Public Utilities Commission of Ohio: Data centers returning to AEP Ohio's standard service give 180 days' notice and bear the power cost (release, docket).
- Supreme Court of Ohio: Ashville's referendum on its EdgeConneX resolution ordered to the board of elections (opinion).
- Plain City council: One-year moratorium on data center applications (minutes).
- Pataskala council: Aligned Data Centers' plan disapproved, 7-0 (minutes).
- Johnstown council: Tax abatement area covering data center buildings widened by about 170 acres (ordinance).
- Grove City council: Public-vote amendment for projects over 20 MW sent to the ballot, 7-0, with a resolution opposing it (minutes).
- Johnstown council: Charter ban on data centers set for a 5 January 2027 election (ordinance).
- Regional planning commission: Plats extended for the Thomas and Starkey complexes, Jerome Township (minutes).
- Grove City council: Innovation district created without data processing among its uses, 7-0 (minutes).
- Heath council: Charter ban petitions rejected for too few signatures (minutes).
- Columbus council: Peak rates for large users, data centers named, due by 26 October, 9-0 (ordinance, minutes).
Reported (7)
Press reports, planning cases with no filing date and records outside the counting rule. None of these is in the counts above.
- Harvey Farms, Etna Township. A 397.3-acre rezoning for "a 397.3-acre data center facility", tabled twice by county planners (staff report). Its filing date is not in the records.
- Aligned Data Centers, Pataskala. Three data center buildings on 89.41 acres, disapproved on 25 August (staff report). Filed in 2025 on a date not shown.
- Project Cosmos, Marysville. A data center exterior plan approved on 15 January 2025 (minutes). No filing date on record.
- Fairfield Energy Center, Millersport. A 1,300 MW gas plant for "a data center adjacent to the project site" (docket). No record names the data center.
- Neo Power, Jersey Township. A 500 MW gas plant applied for in June (docket). No record names a data center.
- Hartman Farms line, Hamilton Township, near Lockbourne. Power lines for a customer of up to 688 MW on Magellan LLC land (construction notice). The record does not say data center.
- Stream Data Centers, Grove City and Jackson Township. About 300 acres reported in the press. No local record names it.
Coverage and method
Boundary. The ten counties of the Columbus metropolitan area as the federal government defines it: Delaware, Fairfield, Franklin, Hocking, Licking, Madison, Morrow, Perry, Pickaway and Union.
| Authority | Records | Status, Q1 2025 to Q3 2026 |
|---|---|---|
| City of Columbus | Building permits and site plans naming a data center | Counted. A filing that never names a data center is missed |
| Jerome Township | Zoning certificates for new buildings | Counted |
| New Albany, Pataskala, Commercial Point and other cities and villages | Planning and council records | Counted where a case names a data center and gives a filing date |
| Licking, Union and Hilliard building permits | Building permits | Not in the count. They are not searchable online |
| Licking, Franklin and Union county planning bodies | Planning commission and commissioner records | Read for 2026, partly for 2025 |
| Ohio Power Siting Board | Power plant applications naming the data center served | Counted, dated by the application |
| Ohio EPA | Air permits for data center generators and plants | Listed, not counted. The records show permit dates, not filing dates |
| Madison, Morrow, Hocking and Perry counties | None | Not collected |
What is counted. Only work that adds data center buildings or capacity: new buildings and planning cases naming a data center, and power plants over 1 MW whose records name the data center they serve. Replacements, repairs, renewals and amendments do not count, nor do planning cases whose records give no filing date.
Counting. A site is one address or one campus and counts once in a quarter however many filings it makes. Meta's three power plants for its Sidecat campus are one site, and so are the Thomas and Starkey complexes in Jerome Township, which share an owner and a boundary. A power plant case is dated by its application, not the notice that opens its docket.
Sources and revisions
Every figure links to the public record it came from: a permit, a planning case, a state docket or the minutes of the body that acted. Company statements are named as such and never counted on their own.
Colocation Scout is run by a wholesale and colocation consultant. The permit data is public and every row links to its filing. How we publish these reports.
Revisions: none yet. Edition status: final.
Cite this report as: Colocation Scout, "Columbus data center permits, Q3 2026," colocationscout.com/reports/columbus-data-center-permits-q3-2026.html