Q3 2026 Market Report / Atlanta

Four Atlanta-area sites filed for data center campuses or buildings in Q3 as thirteen local governments paused new projects.

An interim report from the state's regional impact register, local permit, planning and board records, and state air permits.

Interim edition from the state's regional impact register for all 29 counties, City of Atlanta, Gwinnett, Clayton, Rockdale and Newton permit records, Douglas County's issued-permit reports, county and city board records, and Georgia EPD air permits. The metro total of local permits is unknown. See the coverage and method.

4

sites filed for new data center campuses or buildings in Q3 in the records reviewed: two campuses entered the state's regional impact review, DC Blox applied for a building in Rockdale and Project Peach filed construction drawings in Coweta. The metro total of local permits is unknown.

13

local governments adopted or extended a data center moratorium in Q3, among them DeKalb, Cobb and Cherokee counties and the cities of Marietta and Roswell.

2

county boards denied data center campuses, in Douglas and Coweta, while Cartersville and Marietta approved projects.

Microsoft and Thor Acquisition sent campuses to the state's regional review, DC Blox and Coweta's Project Peach filed for buildings, and thirteen local governments paused new data center applications.

Map of the Atlanta metro area. Planning markers show two campuses sent to the state's regional impact review in Q3 2026: the Kingston Technology Hub in Bartow County, filed September 4 and placed at the center of Kingston because its record gives a parcel number only, and Microsoft's ATL50 on Stonewall Tell Road, filed September 15. A permit marker shows the DC Blox ATL-2C building application on Farmer Road in Rockdale County, filed September 22, and a plans marker shows Project Peach construction drawings near Palmetto in Coweta County, filed September 30. Lighter markers show the DataBank campus in Cartersville and the Powers Ferry Place site in Marietta, both filed before the quarter and approved in it. Pause markers, two of them shared by a county and a city inside it, show the thirteen local governments that adopted or extended a data center moratorium in the quarter: DeKalb, Cobb, Cherokee, Paulding, Carroll, Rockdale, Morgan and Meriwether counties and the cities of Marietta, Roswell, Milton, Forest Park and Madison. Small grey dots are operating data centers from PeeringDB.
A filing is not available space. Marks are the street address on each record or, for Kingston, the town's center. A pause marker is a local government that adopted or extended a data center moratorium in the quarter. Download the map (PNG). Reporters may republish the map with credit to Colocation Scout and a link to this page.
Operating facilities on the map (42)

The small hollow grey dots are data centers listed in the public PeeringDB facility list, each linked to its record. Listings marked closed are left off. A listed building is in no count on this page.

OperatorFacilityCityRecord
365 Data Centers365 Data Centers Alpharetta (GA1)Alpharettapeeringdb.com/fac/16127
365 Data Centers365 Data Centers Smyrna (GA2)Smyrnapeeringdb.com/fac/16132
CentersquareCentersquare Atlanta (ATL1-A/B/C)Lithia Springspeeringdb.com/fac/4048
CentersquareCentersquare Atlanta (ATL1-D)Lithia Springspeeringdb.com/fac/6675
Cogent Communications, Inc.Cogent AtlantaAtlantapeeringdb.com/fac/9622
Cogent Communications, Inc.Cogent Atlanta 2Atlantapeeringdb.com/fac/16444
Colo at 55, LLCColo at 55, LLCAtlantapeeringdb.com/fac/619
Coloblox Data Centers IncColoblox Data Centers ATL1Atlantapeeringdb.com/fac/7938
Coloblox Data Centers IncColoblox Data Centers ATL2Atlantapeeringdb.com/fac/4604
Coloblox Data Centers IncColoblox Data Centers ATL3Atlantapeeringdb.com/fac/6022
CoreSiteCoreSite - Atlanta (AT1)Atlantapeeringdb.com/fac/1337
CoreSiteCoreSite - Atlanta (AT2)Mariettapeeringdb.com/fac/6638
DataBank, Ltd.Databank Atlanta (ATL1)Atlantapeeringdb.com/fac/8484
DataBank, Ltd.DataBank Atlanta (ATL2)Atlantapeeringdb.com/fac/3853
DataBank, Ltd.DataBank Atlanta (ATL3)Atlantapeeringdb.com/fac/10916
DC BLOX Parent LLCDC BLOX ATL1 - DCBLOX AtlantaAtlantapeeringdb.com/fac/7220
Digital RealtyDigital Realty ATL13 - AtlantaAtlantapeeringdb.com/fac/125
Digital RealtyDigital Realty ATL14 - AtlantaAtlantapeeringdb.com/fac/3725
EdgeConneX Inc.EdgeConneX Atlanta (EDCATL01)Atlantapeeringdb.com/fac/1929
EdgeConneX Inc.EdgeConneX Atlanta (EDCATL02)Atlantapeeringdb.com/fac/7568
Equinix, Inc.Equinix AT1 - AtlantaAtlantapeeringdb.com/fac/940
Equinix, Inc.Equinix AT2/AT3 - AtlantaAtlantapeeringdb.com/fac/11
Equinix, Inc.Equinix AT4 - AtlantaAtlantapeeringdb.com/fac/12513
Flexential Corp.Flexential - Atlanta/Alpharetta (ATL3/4)Alpharettapeeringdb.com/fac/4996
Flexential Corp.Flexential - Atlanta/Douglasville (ATL5)Douglasvillepeeringdb.com/fac/13389
Flexential Corp.Flexential - Atlanta/Norcross (ATL1/2)Norcrosspeeringdb.com/fac/4995
H5 Data CentersH5 Data Centers AtlantaAtlantapeeringdb.com/fac/3078
Lincoln RackhouseLincoln Rackhouse AtlantaDunwoodypeeringdb.com/fac/10104
Lumen Technologies IncLevel(3) Atlanta (Courtland)Atlantapeeringdb.com/fac/249
Lumen Technologies IncLevel(3) Atlanta (Peachtree)Atlantapeeringdb.com/fac/1729
PerformiveAtlanta Tech VillageAtlantapeeringdb.com/fac/2269
PerformiveColo@ (Buckhead)Atlantapeeringdb.com/fac/2268
PerformiveColo@34 (Downtown)Atlantapeeringdb.com/fac/1293
PhoenixNAPPhoenixNAP ATLANTAMariettapeeringdb.com/fac/8341
QTS Realty Trust, Inc.QTS Atlanta-Fayetteville (ATL2)Fayettevillepeeringdb.com/fac/16563
QTS Realty Trust, Inc.QTS Atlanta-Metro (ATL1)Atlantapeeringdb.com/fac/581
QTS Realty Trust, Inc.QTS Atlanta-Suwanee (SUW1)Suwaneepeeringdb.com/fac/580
ServerfarmServerfarm ATL1 AtlantaSuwaneepeeringdb.com/fac/5435
Southern TelecomSouthern TelecomAtlantapeeringdb.com/fac/15861
T5 Data CentersT5@AtlantaLithia Springspeeringdb.com/fac/11930
Verizon Communications, Inc.Verizon AtlantaAtlantapeeringdb.com/fac/3951
VPLSEvocative ATL1Atlantapeeringdb.com/fac/5890

What happened this quarter

Four sites filed for new campuses or buildings

Four sites filed for new data center campuses or buildings in Q3 in the records reviewed. Two entered the state's review of developments of regional impact, which every Georgia local government files for large projects. Union City filed Microsoft's ATL50 on September 15: two three-story buildings totalling 910,000 square feet on 88 acres off Stonewall Tell Road. Kingston filed the Kingston Technology Hub on September 4, one building of about 350,000 square feet on 559 acres. A third, Stillwater Technology Park in Lovejoy, about 3,465,000 square feet, was filed on July 22 and withdrawn on August 10. In Rockdale, DC Blox applied on September 22 for the shell of a further building on its Farmer Road campus. In Coweta, construction drawings for Project Peach, a campus rezoned in April 2025, were filed on September 30.

Two counties turned campuses down, two cities approved projects

Two county boards denied data center campuses. Douglas County's commissioners denied East Village Dothan, about 4.5 million square feet on some 700 acres near Villa Rica, by 4-1 on July 7, and Coweta's board denied LDO Coweta's five-building campus on Walt Sanders Road by 5-0 on August 25. DeKalb's commissioners denied 7-0 on August 13 a special land use permit for utility structures on Loveless Place in Ellenwood, a site its staff report describes as a one million square foot data center campus. Cartersville went the other way on September 3, rezoning DataBank's Industrial Park Road site by 6-0 after a June regional filing that states 200 MW of critical IT load. Marietta approved a data infrastructure use for part of a building at 1155 Powers Ferry Place on August 12. Rockdale heard the Project Rockforge campus on September 24, with no decision recorded in the quarter.

Thirteen local governments paused new projects

Thirteen local governments adopted or extended a data center moratorium in the quarter. DeKalb extended its pause in July, Cobb extended its own by up to 180 days, and Cherokee adopted a 30-day moratorium in July and a 180-day one in August. Marietta, Roswell, Milton, Paulding, Carroll, Rockdale, Forest Park, Meriwether, Morgan County and Madison also acted. Others wrote rules instead: South Fulton replaced its data center ordinance, Roswell, Dawson and Bartow adopted standards, and Chattahoochee Hills removed data processing from its zoning uses. Atlanta's council has held a proposed exception for a data center site in Adair Park in committee since July.

More data halls inside existing buildings, and a gas plant for a data center

No new data center building was filed in the City of Atlanta in Q3. The city's filings add data space inside existing buildings. An Edged application filed on August 20 would fit out data halls on two floors at 1968 Marietta Road, at an estimated $44,445,616 as filed, and filings at 55 Marietta Street in July and September would convert office floors to data facilities. In Newton County, the state issued an air permit on September 18 for a 90 MW gas-fired plant on Hazelbrand Road that the permit says will supply prime power to a nearby Serverfarm facility. Two days earlier the state had settled with its developer, VoltaGrid, over engines installed before a permit.

The quarter's filings

SiteSquare feetEstimated cost, as filedPower, as filed
Kingston Technology HubKingston, Bartow County. One building350,000About $1,000,000,000“Approximately 150 Megawatts per day”
ATL50Union City, Fulton County. Two buildings910,000TBATBA
DC Blox ATL-2CFarmer Road, Rockdale County. One buildingTBATBATBA
Project Peach construction drawingsPalmetto area, Coweta County. Building count not statedTBATBATBA
Total, 4 sites1,260,000 (2 of 4 sites)$1,000,000,000 (1 of 4 sites)Not added

TBA marks a figure the record does not state yet. Estimated cost, as filed, is the filers' own unverified figure, not total project spend. Power is quoted as the form words it.

Sites filing to add data center capacity, by quarter

A site counts once in a quarter however many permits it files. The counts come from the state's regional impact register, which covers every local government in the 29 counties but only projects above its size thresholds, from building permits in the City of Atlanta and the Gwinnett, Clayton, Rockdale and Newton registers, and from local planning applications that carry a filing date. Many cities and counties publish no searchable permit register, so a quarter can be missing a filing.

Earlier quarters, from the records we have

These counts come from the records we could search for each quarter. Some sources only start partway through, so read them as what the records show, not as a trend.

QuarterAtlanta metro: sites filing to add capacity
Q2 20263
Q1 20265
Q4 20254
Q3 20254
Q2 20256
Q1 20258
Filings and decisions by quarter
QuarterFilings for new data center sites or buildingsDecisions on data center sites, and moratoria
Q1 2025City of Atlanta: QTS ATL-DC4 fit-out, four 3 MW pods, Edged ATL01-3 shell
Coweta: Central Coweta Industrial Phase II
Newton and Walton: Newton County Technology Park, Social Circle Technology Park
Douglas: Hickman Property (East Village Dothan)
Newton: Gregory Road Data Center
Spalding: Project Spalding
Bartow: Project Bunkhouse
Covington annexed and zoned 10835 Hazelbrand Road to allow a data center, 5-1
Social Circle approved the Sailfish data center campus
Fairburn denied the Bohannon Road data center
Douglas County approved the TC Atlanta data center campus
Douglas County adopted a 90-day data center moratorium
Hampton approved a conditional use for the Henderson Farms data center campus
Q2 2025Carroll: Avemore
Rockdale: Project Rockforge
Fulton: T5 ATL IV, 1611 Ellsworth
Clayton: ATL 15 and 16
Social Circle: WSG Land, Fairplay Road
Palmetto adopted an industrial moratorium that includes data centers
Coweta County approved the Project Peach rezoning, 3-2
College Park approved a data center conditional use at 4570 Edison Drive, 4-0
Coweta County adopted a data center moratorium
Douglas County approved Stack Phase 2
Villa Rica approved the Avemore annexation and rezoning
Bartow County: Atlas Development withdrew its 630-acre rezoning
Social Circle approved the 708 Highway 11 data center special use
Bartow County approved Project Bunkhouse
Bartow County approved the Freeman Gaines Road data center rezoning
Marietta approved the Bells Ferry Road data center campus, 7-0
Douglas County extended its data center moratorium
Q3 2025Social Circle: WSG Land, Mill Road and Cannon Drive, Hawkins Academy and Roy Malcom roads, GA Strouds Creek Land, Lakewood Drive, Dermody campus, East Hightower TrailCartersville annexed land into the Switch campus
Douglas County approved the Stream Winston campus, 3-2
DeKalb County adopted a data center moratorium, 4-3
Spalding County approved the Project Spalding rezonings
South Fulton approved the Stonewall Tell data center rezoning, 6-1
Clayton County adopted a data center moratorium, 5-0
Social Circle approved the Fairplay Road and Mill Road data centers and denied the Cannon Drive annexation
Social Circle adopted a 90-day data center moratorium
Q4 2025Butts: Highway 16 Interstate Health Development
Rockdale: DC Blox ATL2 building
Newton: Stanton Springs MWG 7 building
Clayton: 4350 E Tanners Church Road shell
Coweta County extended its moratorium and set a hearing on possibly rezoning the Project Peach site, 4-1
Spalding County approved the 585 Spalding Investments campus
Social Circle approved the Hawkins Academy and Roy Malcom data center site
Social Circle approved the Dermody and Lakewood Drive data center campuses
Douglas County denied East Village Dothan, 4-1
Cartersville annexed 82 Bates Road into the Switch campus
South Fulton adopted a six-month data center moratorium, 7-0
Clayton County extended its data center moratorium
DeKalb County extended its data center moratorium
Peachtree Corners approved the Flexential expansion, 6-0
Union City approved the TA Realty data center rezonings on Red Oak Road, 2-1
Fayetteville rezoned the QTS East Campus
Q1 2026Spalding: Wallace Jackson Data Center Campus
Fayette: ATL2 East
Social Circle: 1402 Roy Malcom Road, added to the Hawkins Academy site
Henry: Hampton Technology Park, Henderson Farms
Covington adopted a 180-day data center moratorium
Palmetto denied T5's data center exemption from its moratorium
Roswell adopted a data center moratorium
Rockdale County adopted a data center moratorium
Griffin adopted a data center moratorium, 7-0
Covington denied the Alcovy Rise annexation
Spalding County approved the Wallace Jackson data center campus
Fayetteville adopted a 90-day data center moratorium
Hampton adopted a 120-day data center moratorium, 6-0
Newton County adopted an emergency data center moratorium, 5-0
Cobb County adopted a data center moratorium, 5-0
Meriwether County adopted a data center moratorium
Douglas County denied Big Power Developments 5, 5-0
Carroll County adopted a 100-day data center moratorium
Fayetteville prohibited data centers in every zoning district
Heard County adopted a 180-day data center moratorium
Lamar County extended its data center moratorium, 4-0
Q2 2026Coweta: Bridgeport (revised)
Bartow: DataBank Project Indo
Morgan: Data center rezoning application, site not named
Coweta County approved Project Sail, 3-2
Newton County extended its data center moratorium to October 7, 5-0
Roswell extended its data center moratorium, 6-0
Hampton approved the Henderson Farms concept plan, 6-0
Social Circle approved the 1402 Roy Malcom Road addition
McDonough adopted a data center moratorium, 6-0
South Fulton extended its data center moratorium to September 9
Rockdale County extended its data center moratorium
Carroll County extended its data center moratorium by 100 days
DeKalb County extended its data center moratorium, 5-2
East Point extended its data center moratorium, 6-0
Milton adopted a 30-day data center moratorium
Coweta County adopted a 180-day data center moratorium, 5-0
Spalding County: the 75 South data center applications were withdrawn
Q3 2026Bartow: Kingston Technology Hub
Fulton: ATL50
Rockdale: DC Blox ATL-2C building
Coweta: Project Peach construction drawings
Douglas County denied East Village Dothan, 4-1
DeKalb County extended its data center moratorium, 6-1
Morgan County adopted a 120-day data center moratorium
Marietta adopted a data center moratorium, 7-0
Forsyth County revoked a data center conditional use permit, 4-0
Madison adopted a four-month data center moratorium, 5-0
Roswell extended its data center moratorium by 90 days
Milton extended its data center moratorium by up to 180 days
Cherokee County adopted a 30-day data center moratorium
Paulding County adopted a data center moratorium, 5-0
Meriwether County extended its data center moratorium
Carroll County extended its data center moratorium
Cobb County extended its data center moratorium, 5-0
Marietta approved a data infrastructure use at 1155 Powers Ferry Place
DeKalb County denied a special land use permit for utility structures on Loveless Place, 7-0. Its staff report describes a data center campus
Cherokee County adopted a 180-day data center moratorium, 5-0
Coweta County denied the LDO Coweta campus, 5-0
Rockdale County extended its data center moratorium on August 25, to October 1
Forest Park adopted a 90-day data center moratorium, 3-0
Cartersville rezoned the DataBank site, 6-0
Rockdale County extended its data center moratorium on September 22, to October 9

Regional impact filings are dated by the local government's submission, and local permits and applications by their filing date. The register shows no data center filing in the metro from July to mid October 2025.

What to watch next

  1. October 2026. Coweta's board is to hold a hearing at its second October meeting, date to be set, on possibly rezoning the Project Peach site. Published record.
  2. October 26, 2026. Kingston's council is scheduled to hold its first hearing on annexing 561.51 acres, the Kingston Technology Hub site, with final action set for November 2. Published record.
  3. November 6, 2026. Comments close on the state air permit application for Amazon's ATL 114 campus on South Flat Rock Road in Douglasville. Published record.

The records behind the findings

The quarter's filings, in detail (4)

Kingston Technology Hub

Location
Bartow County tax parcel 0037-0197-001, about 559 acres. The City of Kingston submitted the filing.
Developer
Thor Acquisition WC LLC
Work, as filed
“One (1) Approximately 350,000 Square Foot Proposed Data Center Facility”
Power, as filed
“Approximately 150 Megawatts per day”, from the Municipal Electric Authority of Georgia
Estimated cost, as filed
“Approximately $1 Billion USD”
Filing and status
Development of regional impact submitted September 4, 2026, for a rezoning. The regional commission's finding is dated September 29.
Record
DRI 4835

ATL50

Location
5235 Stonewall Tell Road, west of Stonewall Tell Road and north of Koweta Road
Developer
Microsoft
Work, as filed
“a data center development on 88.01 acres of land that consists of two, 3-story buildings totaling 910,000 square feet”
Filing and status
Development of regional impact submitted by Union City on September 15, 2026, for a permit and master plan review. Only the initial form is on record. Buildout is listed as 2032.
Record
DRI 4843

DC Blox ATL-2C

Location
1726 Farmer Road NW, Conyers, on the DC Blox Atlanta East campus
Owner of record
Dcb Atlanta East LLC
Work, as filed
“DC Blox ATL- 2C - Core and Shell Permit” for “a cold dark shell”, with no mechanical, electrical or plumbing plans
Filing and status
Building permit application created September 22, 2026, not yet issued. The register row gives no square footage or power. A two-story, 192,437-square-foot building on the same campus was filed in October 2025.
Record
Rockdale County permit register, web case 55690

Project Peach construction drawings

Location
200 Johnston Circle, Palmetto, in unincorporated Coweta County
Project
Project Peach, a data center campus of about 2.1 million square feet that Coweta rezoned on April 15, 2025. The drawings record names only “Project Peach”.
Work, as filed
“Construction Drawings”, with offsite sewer drawings filed the same day
Pending hearing
On October 21, 2025 Coweta's board voted 4-1 to hold a hearing at its second October 2026 meeting on possibly rezoning the site back to rural use, under a condition of the rezoning, giving the owner 12 months to obtain a power purchase agreement.
Filing and status
Construction drawings filed September 30, 2026, in review. The public record states no square footage, building count or power.
Record
CD-26-062
Every data center project with a dated record, Q1 2025 to Q3 2026 (61)
Site and recordsAuthorityFirst filedPermit first issuedDeclared valueScope
Stillwater Technology Park / DRI 4794LovejoyJuly 22, 2026Withdrawn August 10, 2026$13,000,000,000About 3,465,000 sq ft of data center buildings
Kingston Technology Hub / DRI 4835KingstonSeptember 4, 2026Planning case, not decidedAbout $1 billionOne building of about 350,000 sq ft on 559 acres
ATL50 / DRI 4843Union CitySeptember 15, 2026Planning case, not decidedNot statedTwo buildings, 910,000 sq ft, 88 acres
DC Blox Atlanta East campus / 25-012274
web case 55690 ATL-2C core and shell, filed September 22, 2026
RockdaleOctober 15, 2025ATL2 issued December 30, 2025. ATL-2C not issuedNot statedATL2, 192,437 sq ft, filed October 15, 2025. ATL-2C shell filed September 22, 2026
DataBank Project Indo / DRI 4761
Z26-05 Council rezoning, September 3, 2026
CartersvilleJune 19, 2026Rezoned September 3, 2026$2.4 billion200 MW critical IT load, as filed
Bridgeport (revised) / DRI 4727CowetaApril 28, 2026Regional review completed$3 to $5 billionTechnological facility added to an industrial park. Load request up to 1,500 MW, as filed
Henderson Farms / DRI 4680
CU-25-01-17 conditional use approved March 25, 2025
HamptonMarch 24, 2026Regional review completed$650 millionMixed-use tract with a data center campus, 200 MW as filed
Hampton Technology Park / DRI 4624HamptonFebruary 13, 2026Regional review completed$12 billionFive buildings, 4,000,000 sq ft, 603.56 acres, 1,500 MW peak as filed
The Crossings / DRI 4617Union CityFebruary 12, 2026Review terminatedNot statedData center development on 231.8 acres
75 South Data Center Campus / DRI 4607
withdrawal letter 26-01FLUM, 26-01Z, 26-01S and 26-07V withdrawn, June 25, 2026
SpaldingJanuary 27, 2026Applications withdrawn June 25, 2026. The applicant said it would refile$6 billionSeven buildings, 2,240,000 sq ft, 450 MW as filed
Project Bus / DRI 4606TempleJanuary 26, 2026Withdrawn$11 billion12 buildings and two substations on 350.73 acres
ATL2 East (QTS) / DRI 4603
25-O-34 QTS East Campus rezoning approved December 18, 2025
FayettevilleJanuary 13, 2026Regional review completed$3 billion2,000,000 sq ft data center west of Veterans Parkway
Wallace Jackson Data Center Campus / DRI 4599SpaldingJanuary 6, 2026Regional review completed$3,650,000,000Ten buildings, 4,986,000 sq ft
4350 E Tanners Church Road / BCOM-1225-01957ClaytonDecember 11, 2025In review in the 2025 file$24,458,250Building shell, 309,911 sq ft. A Data Hall 2 permit followed on August 11, 2026
Stanton Springs MWG 7 / CBP25-001118Newton (for the Stanton Springs authority)October 23, 2025Issued October 23, 2025Not statedNew data center building, tensioned membrane structure. The record places it in Morgan County
Flexential expansion, Peachtree Corners / SUP2025-002Peachtree CornersLetter of intent dated October 1, 2025Approved December 16, 2025Not statedExpansion into 2755 Northwoods Parkway, four 1.5 MW blocks as filed
Highway 16 Interstate Health Development / DRI 4560ButtsOctober 14, 2025Regional review completed$10 billionMixed-use development naming data center use, about 11 million sq ft in all
1611 Ellsworth / DRI 4506City of AtlantaJune 30, 2025Regional review completed$1 billionMixed-use plan naming a data center
ATL 15 and 16 (Digital Realty) / DRI 4482Forest ParkMay 30, 2025Regional review completed$2.55 billionAbout 1,902,657 sq ft on 97 acres at Fort Gillem
T5 ATL IV / DRI 4465FairburnMay 5, 2025Regional review completed$3.2 billionSix data center buildings
Project Rockforge / DRI 4456
REZ2025-08 county rezoning, filed April 22, 2025
RockdaleApril 14, 2025Heard September 24, 2026, no decision recorded in the quarter$8,953,374,500Eight buildings, 4,089,000 sq ft in the regional filing. Seven buildings, 2,961,000 sq ft in the county hearing packet
Avemore / DRI 4451Villa RicaApril 11, 2025Rezoned May 2025More than $45 millionTechnology campus and data park
Project Bunkhouse / DRI 4433BartowMarch 31, 2025Rezoned June 4, 2025$19 billionEight data center buildings
Project Spalding / DRI 4425SpaldingMarch 28, 2025Rezoned July 14, 2025$1,875,000,000Data center campus
Gregory Road Data Center / DRI 4428CovingtonMarch 27, 2025Regional review completed$5.7 billionUp to 1,410,000 sq ft on about 213 acres
Hickman Property (East Village Dothan) / DRI 4422
M2026-01, Z2026-56, S2026-57 denied 4-1, July 7, 2026
DouglasMarch 14, 2025Denied December 2, 2025, and July 7, 2026$24.9 billionAbout 700 acres, 4.5 million sq ft in the county case
Project Springbank / DRI 4403BartowFebruary 14, 2025Rezoning withdrawn May 14, 2025$4.5 billionSix buildings, 2,274,000 sq ft
Social Circle Technology Park / DRI 4376
DRI 4426 refiled by Social Circle, March 21, 2025
Newton, then Social CircleJanuary 16, 2025Regional review completed$5 billionNine buildings, 2,567,040 sq ft
Central Coweta Industrial Phase II (LDO Coweta) / DRI 4374
REZ 24-20 denied 5-0, August 25, 2026
CowetaJanuary 15, 2025Denied August 25, 2026$4 billionEight data center buildings, 2,388,800 sq ft in the regional filing. Five buildings, 1,828,368 sq ft in the amended county case
Edged ATL01-3 shell / BB-202501970City of AtlantaMarch 5, 2025Issued$50,000,000New one-level 217,682 sq ft shell at 1740 Thomas Street
QTS ATL-DC4 fit-out / BB-202500047City of AtlantaJanuary 3, 2025Certificate of occupancy issued$30,000,000Data hall fit-out with four 3 MW pods, as described
ATL 088, Rock House Road / Douglas, February 2026 reportDouglasNot in the issued reportIssued February 4, 2026$310,000,000New building shell and interior, 414,000 sq ft
AWS 071 Building 4, T5 ATL III campus / 2402778DouglasNot in the issued reportIssued August 27, 2026$23,333,333Shell only, 427,456 sq ft
Edged data hall fit-out, Marietta Road / BB-202607320City of AtlantaAugust 20, 2026In review$44,445,616Data hall fit-out of two floors at an existing building. The filing does not state added power in its description
55 Marietta Street office conversions / BB-202606258
BB-202607720 17th floor conversion, filed September 2, 2026, $2,000,000
City of AtlantaJuly 17, 2026In review$16,800,000Office floors converted to a data facility
Switch NAP04 data hall racking / 2601601DouglasNot in the issued reportIssued July 2, 2026$5,000,000Area 7 data hall racking, 41,957 sq ft, at 1 Switch Way. No added power stated
WSG Land data center, Fairplay Road / SU-2025-005Social CircleJune 17, 2025Approved September 16, 2025Not statedAnnexation, rezoning and special use for a data center
WSG Land data center, Mill Road / SU-2025-006
September 16, 2025, council decisions
Social CircleJuly 1, 2025Mill Road approved September 16, 2025. Cannon Drive annexation deniedNot statedRezoning and special use for a data center
Hawkins Academy and Roy Malcom roads data center / SU-2025-007
SU-2026-001 1402 Roy Malcom Road added, filed February 9, 2026, approved April 21, 2026
Social CircleAugust 12, 2025Approved November 6, 2025Not statedAnnexation, rezoning and special use for a data center
Dermody data center campus, East Hightower Trail / SU-2025-008Social CircleSeptember 15, 2025Approved with conditions November 18, 2025Not statedSpecial use for a data center campus
GA Strouds Creek Land data center campus, Lakewood Drive / SU-2025-009Social CircleSeptember 2025Approved November 18, 2025Not statedAnnexation, rezoning and special use for a data center campus
Sailfish data center campus, Amber Stapp Studdard Road / SU-2024-001Social CircleNovember 15, 2024Approved January 22, 2025Not statedAnnexation, rezoning and special use for a data center campus
Morgan County data center application / Staff report, August 2026MorganJune 30, 2026Incomplete, under the county's moratoriumNot statedRezoning for a data center. The record does not name the applicant or site
585 Spalding Investments data center campus / 25-22ZSpaldingNot on record (first hearing June 24, 2025)Rezoned October 23, 2025Not statedData center campus at 50 S McDonough Road
Stack Phase 2 (SAC III Acquisitions) / Z2025-47DouglasNot on record (heard May 6, 2025)Approved May 6, 2025Not statedData center rezoning and special use, Factory Shoals Road and Linda Lane
Stream Winston campus (SDC ATLA) / Z2025-55DouglasNot on record (first hearing June 3, 2025)Approved July 8, 2025Not statedData center rezoning and special use. The site's regional filing was in 2024
Amazon Data Services, Strickland Street / RES-2025-43DouglasvilleNot on recordHeight variance approved September 2, 2025Not statedVariance for a data center site of 132.2 acres
Big Power Developments 5, Rockhouse Road / S2025-13DouglasNot on record (first listed April 2025)Denied March 3, 2026Not statedSpecial use for a data center
Stonewall Tell data center rezoning / Z25-002South FultonNot on record (first council reading, January 14, 2025)Approved August 12, 2025Not statedCity-initiated data center rezoning and special use, Mason Road and Stonewall Tell Road
Freeman Investments, Gaines Road / Z-25-00015BartowNot on recordApproved June 4, 2025Not stated122 acres rezoned with data center as the only allowed use
MMM Acquisitions, 1751 Bells Ferry Road / Z2025-11MariettaNot on recordApproved June 11, 2025Not statedData center campus with a substation on 31 acres
Prime Storage, 1155 Powers Ferry Place / Z2026-12MariettaNot on record (planning commission July 1, 2026)Approved August 12, 2026Not statedData infrastructure use in part of an existing building
TC Atlanta campus, Veterans Memorial Highway / Z2024-55Douglas2024Approved February 4, 2025Not statedData center rezoning and special use
Project Peach (Weldon Road) / REZ 24-14
CD-26-062 construction drawings, filed September 30, 2026
CD-26-063 offsite sewer drawings, filed September 30, 2026
Coweta2024Rezoned April 15, 2025. Construction drawings in reviewNot statedData center rezoning, 2.1 million sq ft
Project Sail, Welcome to Sargent Road / REZ 24-19CowetaDecember 2024Approved April 7, 2026Not statedData center rezoning on 829 acres
PCC-DeKalb, Loveless Place, Ellenwood / SLUP-25-1247635
2025-0970 board history
DeKalbJune 25, 2025Special land use permit for utility structures denied 7-0, August 13, 2026Not statedThe county staff report says the site plan shows a one million sq ft data center campus with a substation on 95 acres
Alcovy Rise, 600 Elks Club Road, Covington / PAR25.0004CovingtonNot on record (Newton objected October 21, 2025)Annexation denied January 20, 2026Not statedAnnexation of 1,522.68 acres for a data center
Hazelbrand Road data center site, Covington / Annexation and M2 zoningCovingtonNot on recordApproved 5-1, January 6, 2025Not stated95.556 acres annexed and zoned to allow a data center at 10835 Hazelbrand Road
CleanSpark data center, 4570 Edison Drive, College Park / CUP, item 9D
April 21, 2025, packet staff report and ordinances, 1.98 acres for a data center
College ParkNot on record (planning commission hearing March 31, 2025)Conditional use and rezoning approved 4-0, April 21, 2025Not statedConditional use for a data center on 1.98 acres. The applicant stated 36 MW across six units at the hearing
TA Realty data center, Red Oak Road, Union City / Items E, F and G, December 16, 2025Union CityNot on record (first on the September 2025 agenda)Approved 2-1, December 16, 2025Not statedThree rezonings to OI totalling 67.786 acres for a data center, four buildings per staff
3600 International Drive, DeKalb / 1248045DeKalbMarch 6, 2026Not accepted under the county's moratoriumNot statedLand disturbance revision to regrade a studio campus for future data center buildings
State air permit applications (4)
ReceivedFacility and recordStatusWhat the record states
September 18, 2026VoltaGrid ATL-1 EGU, Hazelbrand Road, Covington / 4911-217-0080-S-01-0IssuedA new 90 MW natural gas plant of 33 engines. The permit says it will provide prime power to a nearby Serverfarm facility.
August 2026Amazon Data Services ATL088 Campus, 2341 Echo Road, Lithia Springs / 30292Application, comments closed September 25To construct and operate a data center. The notice states no generator count.
July 2026The Keep 2 Campus (Switch), Bates Road, Cartersville / 30076Proposed permit, comments closed August 7Additional emergency generators at an existing campus. No capacity stated.
August 2026The Keep 2 Campus (Switch), Bates Road, Cartersville / 30289Application, comments closed September 25Additional main generators at an existing campus. No capacity stated.

An air permit covers generators or a power plant, not data center floor space.

Government actions and review milestones (29)
DateAuthorityEvent
July 1Bartow CountyNoise and cooling rules
July 7DeKalb CountyMoratorium extended, 6-1
July 7Douglas CountyEast Village Dothan denied, 4-1
July 7Morgan CountyMoratorium adopted
July 8MariettaMoratorium adopted, 7-0
July 9Forsyth CountyData center permit revoked, 4-0
July 13Atlanta council committeeAdair Park exception held, 6-1
July 13MadisonMoratorium adopted, 5-0
July 13RoswellMoratorium extended
July 20MiltonMoratorium extended
July 21Cherokee CountyMoratorium adopted
July 28Meriwether CountyMoratorium extended
July 28Paulding CountyMoratorium adopted, 5-0
August 4Carroll CountyMoratorium extended
August 6Dawson CountyData center rules, 4-0
August 10RoswellData center rules, 5-0
August 11Cobb CountyMoratorium extended, 5-0
August 11South FultonData center ordinance replaced
August 12MariettaPowers Ferry Place approved
August 13DeKalb CountyLoveless Place permit denied, 7-0
August 18Cherokee County180-day moratorium, 5-0
August 25Coweta CountyLDO Coweta denied, 5-0
August 25Rockdale CountyMoratorium extended
August 31Forest ParkMoratorium adopted, 3-0
September 1Chattahoochee HillsData processing use removed
September 3CartersvilleDataBank rezoned, 6-0
September 18Georgia EPDVoltaGrid air permit issued
September 22Rockdale CountyMoratorium extended
September 24Rockdale CountyRockforge heard, no decision

All dates are 2026. A hearing or recommendation is not an approval.

Reported

These projects have been reported, but a decision, a filing or the data center use is still open for each.

Coverage and method

Boundary: the Atlanta-Sandy Springs-Roswell metropolitan statistical area as the federal government defined it in 2023: Barrow, Bartow, Butts, Carroll, Cherokee, Clayton, Cobb, Coweta, Dawson, DeKalb, Douglas, Fayette, Forsyth, Fulton, Gwinnett, Haralson, Heard, Henry, Jasper, Lamar, Meriwether, Morgan, Newton, Paulding, Pickens, Pike, Rockdale, Spalding and Walton counties, with every city in them.

AuthorityRecords reviewedCoverage
Georgia DCA, developments of regional impactEvery regional impact filing in the 29 countiesComplete for all seven quarters.
City of AtlantaBuilding and planning records, council legislationComplete for all seven quarters.
Douglas CountyMonthly issued-permit reports, board minutesBoard records complete. Permit reports for January to August 2025 are not posted online.
Gwinnett, Clayton, Rockdale and Newton countiesPublic permit registers, board recordsComplete for all seven quarters.
Cobb, Cherokee, Coweta, DeKalb, Fayette, Spalding, Bartow and other county boardsBoard and planning agendas and minutesComplete where minutes are posted. Several counties publish no searchable permit register.
CitiesCouncil and planning records in about 60 citiesPartial. Some cities post no minutes, or none for part of the period.
Georgia EPDAir permits and enforcement ordersComplete for issued permits. Weekly application notices read from January 2025, with three issues not posted.

Full: every relevant local record for the quarter was read in that county. Partial: some authorities in the county publish no searchable permit register, or post scanned or no minutes, so the quarter may be missing a filing. The state register is complete for every county in every quarter.

AuthorityQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
BarrowPartialPartialPartialPartialPartialPartialPartial
BartowPartialFullPartialPartialFullFullPartial
ButtsPartialPartialPartialPartialPartialPartialPartial
CarrollFullFullFullFullFullFullFull
CherokeePartialPartialPartialPartialPartialPartialPartial
ClaytonPartialPartialPartialPartialPartialPartialPartial
CobbFullFullFullFullFullFullFull
CowetaPartialPartialPartialPartialPartialPartialPartial
DawsonPartialPartialPartialPartialPartialPartialPartial
DeKalbPartialPartialPartialPartialPartialPartialPartial
DouglasPartialPartialPartialPartialPartialPartialPartial
FayettePartialPartialPartialPartialPartialPartialPartial
ForsythFullFullFullFullFullFullFull
FultonPartialPartialPartialPartialPartialPartialPartial
GwinnettPartialPartialPartialPartialPartialPartialPartial
HaralsonPartialPartialPartialPartialPartialPartialPartial
HeardFullFullFullFullFullFullFull
HenryPartialPartialPartialPartialPartialPartialPartial
JasperPartialPartialPartialPartialPartialPartialPartial
LamarPartialPartialPartialPartialPartialPartialPartial
MeriwetherPartialPartialPartialPartialPartialPartialPartial
MorganPartialPartialPartialPartialPartialPartialPartial
NewtonPartialPartialPartialPartialPartialPartialPartial
PauldingFullFullFullFullFullFullFull
PickensFullFullFullFullFullFullFull
PikePartialPartialPartialPartialPartialPartialPartial
RockdalePartialPartialPartialPartialPartialPartialPartial
SpaldingPartialPartialPartialPartialPartialPartialPartial
WaltonPartialPartialPartialPartialPartialPartialPartial

A site is one address or campus, listed in the quarter its record shows a filing to add data center buildings: a regional impact filing, rezoning or other planning application for a new campus, or a permit for a new building. Work inside an existing data center building is listed with the power it states. A filing later withdrawn or terminated is listed in the records but not in the quarterly counts.

Since December 15, 2025, the state register covers data centers above 300,000 square feet or 200 acres in the Atlanta Regional Commission's area and above 500,000 square feet or 200 acres elsewhere, so smaller projects can be missing.

This is not a census of every local permit. A filing does not establish construction, and a permit is never available space.

Sources and revisions

Every figure links to the public record it came from: a regional impact filing, a building permit, a zoning case, a board or council record, or a state permit. News coverage is named as news and never stands in for a record. This edition is final. Its figures change only by a dated correction. A correction will name the record it changes.

Colocation Scout is run by a wholesale and colocation consulting company. The permit data is public and every row links to its filing. How we publish these reports.

Revisions: none yet. Edition status: final.

Cite this report as: Colocation Scout, "Atlanta data center filings, Q3 2026," colocationscout.com/reports/atlanta-data-center-permits-q3-2026.html

Media inquiries

Cody Swift
Data Center Advisor at Colocation Scout
Powered by Bridgepointe Technologies
844-506-2299

Research at Colocation Scout

Colocation Scout tracks data center construction across U.S. markets from public records: building permits, planning cases and state air permits. Every figure in a report links to the filing it came from, so any reader can check it. How we publish these reports.